1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Work done yet to be certified is called _____.
work certified
work uncertified
cash received
work in progress
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Profit on incomplete contract is calculated on the basis of _____ of completion.
stage
degree
retention
process
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
On _____ of the contract entire profit is transferred to P & L A/c.
25% completion
50% completion
90% completion
completion
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
__________ is debited to the contract A/c.
Work Certified
Work Uncertified
Cash Received
Sub Contract Cost
5.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Most of the costs in a contract are direct cost.
True
False
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?