PM 1 2.04 Quiz
Authored by Bobbie Jones
Business
9th - 10th Grade
Used 22+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has discovered that a project is outside the original scope. The project manager has requested a change to bring expected future performance of the project work back in line with the project management plan. What type of change implementation has the project manager requested?
corrective action
defect repair
lessons learned
preventive action
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Mary would like to add extra windows to the sunroom project she is having built onto her home. The extra windows were left out of the description she provided when the project began. What should Mary do next?
consult the project sponsor
delay the next scheduled inspection
implement the corrective changes
submit a change request
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A customer calls the project manager and informs her of a minor change to a requirement on the project. What is the first thing that the project manager should do?
analyze the request and its costs on the project
ask the customer to provide a formal change request
instruct her team to implement the minor change
note the change in her weekly notes for review
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
George has described a project to rebuild an antique car. He has defined how much of his personal money he has saved to spend on this project. Kelly will be leading a team that will be executing the deliverables for
the project. Who can approve the project?
project manager
project stakeholders
project sponsor
project team
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is implementing a variety of approved changes to a project. Which would least likely be a type of approved change?
corrective action
defect repair
lessons learned
preventive action
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After discovering that some project work failed to be performed according to plan, a project manager analyzes the situation. She then presents what needs to occur to correct the problems to Austin. Austin requests a change in the project to reduce the probability of negative
consequences associated with project risks. What type of change request is Austin making?
corrective action
defect repair
lessons learned
preventive action
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which term best describes the formal group of stakeholders formed to review, evaluate, approve, delay or reject changes to a project with recorded decisions?
corrective action team (CAT)
preventative action team (PAT)
change control board (CCB)
defective repair board (DRB)
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Financial landscape
Quiz
•
9th Grade
10 questions
Annual Meet -ASNS
Quiz
•
9th - 12th Grade
10 questions
Cover Letter and Résumé Quiz
Quiz
•
8th Grade - University
10 questions
S3 Spreadsheets - Absolute Cell References
Quiz
•
9th Grade
10 questions
Entrepreneurship Quiz
Quiz
•
9th Grade
10 questions
The Consumer: JC Business
Quiz
•
8th - 10th Grade
15 questions
Stock Investing Terms
Quiz
•
9th - 10th Grade
12 questions
Economics recap
Quiz
•
10th Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
29 questions
Alg. 1 Section 5.1 Coordinate Plane
Quiz
•
9th Grade
22 questions
fractions
Quiz
•
3rd Grade
11 questions
FOREST Effective communication
Lesson
•
KG
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade