24-25 PM1 Charter Creation & Decision Making

Quiz
•
Business
•
9th - 12th Grade
•
Hard
Bobbie Jones
Used 79+ times
FREE Resource
17 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Delores is leading a marketing project. She meets with the stakeholders to define and document all the needs for the marketing project. The activity that Delores is participating in is referred to as:
collecting requirements.
controlling the scope.
creating the WBS.
verifying the scope.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Kristi is in charge of planning a charity event for the hospital. She wants to review the requirements of each of the stakeholders. Kristi should be reviewing which document?
requirements documentation
requirements management plan
requirements traceability matrix
work breakdown structure
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Jackie is developing a document that will outline the methods to create and manage requirements, as well as the method used to prioritize requirements. Jackie is working on the:
requirements documentation.
requirements management plan.
requirements traceability matrix.
work breakdown structure.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Sam is an event planner and is considering locations for an annual conference. He has decided to ask the board of directors to vote on two locations, so that whichever location receives over 50% of the group's support will win. Sam is using which technique to collect requirements?
dictatorship
majority
plurality
unanimity
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Kacie is working on a new car design for an automotive company. She is currently working on a way to analyze, document, and manage all the stakeholder requirements for the new design. Kacie is working on the:
requirements management plan.
requirements documentation.
requirements traceability matrix.
work breakdown structure.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Carol is managing a construction project and is considering relocating her team closer to the project construction worksite. She asks the stakeholders to vote on this decision and will make the move only if they all agree to it. Carol is using which tool or technique to collect requirements?
dictatorship
majority
plurality
unanimity
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Peter is working on a respiration project for firefighters. Before finalizing the product requirements, he would like to show a working model to the firefighters at the local station to gather feedback. The technique that Peter should use to test the working model would be a/an:
facilitated workshop.
observation.
prototype.
survey.
Create a free account and access millions of resources
Similar Resources on Wayground
13 questions
PM2-Unit 1 Quiz

Quiz
•
12th Grade
20 questions
PM 3 Test

Quiz
•
12th Grade
20 questions
T-Lev Media CK9 Project Lifecycle Quiz

Quiz
•
11th Grade
20 questions
Business Management Final Review 2

Quiz
•
9th - 12th Grade
12 questions
Project management vocab

Quiz
•
9th - 12th Grade
20 questions
A*S*K Fundamental Business Concepts Practice Test #2

Quiz
•
12th Grade
20 questions
S23 - Business Law - Legal and Ethical Considerations

Quiz
•
12th Grade
13 questions
Project Initiation Documents and Business Cases Quiz

Quiz
•
12th Grade
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade