Inspection and Testing Sample questions

Inspection and Testing Sample questions

1st - 12th Grade

20 Qs

quiz-placeholder

Similar activities

Practica Digital (1ra parte)

Practica Digital (1ra parte)

11th Grade

15 Qs

Test 6 Portable Power Tool Safety

Test 6 Portable Power Tool Safety

10th - 12th Grade

22 Qs

ÔN TẬP CUỐI HỌC KÌ II - MÔN CÔNG NGHỆ

ÔN TẬP CUỐI HỌC KÌ II - MÔN CÔNG NGHỆ

4th Grade

20 Qs

PROGRAMAS TURÍSTICOS

PROGRAMAS TURÍSTICOS

2nd Grade

15 Qs

Penilaian Harian Ke-1 Kelas 9

Penilaian Harian Ke-1 Kelas 9

8th Grade

20 Qs

Quiz Sanlat Gembira

Quiz Sanlat Gembira

3rd Grade

15 Qs

GUIA 2 AUTOEFICACIA PARA LA VIDA

GUIA 2 AUTOEFICACIA PARA LA VIDA

10th Grade

16 Qs

I Love Malaysia

I Love Malaysia

KG - 6th Grade

15 Qs

Inspection and Testing Sample questions

Inspection and Testing Sample questions

Assessment

Quiz

Specialty

1st - 12th Grade

Practice Problem

Medium

Created by

Chris Falet

Used 144+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

1. The non-statutory document that is applicable to the probes and leads of test equipment is:

a. HSE Guidance Note GS 38

b. BS7671

c. The IET On Site Guide

d. IET Guidance Note 3.

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The following tests may be carried out on a new installation:

1. polarity

2. insulation resistance

3. ring final circuit continuity

4. cpc continuity.

The relevant test in the correct sequence for a new ring final circuit are:

a. 2,1,4

b. 1,2,4,3

c. 3,1,2

d. 3,2,1.

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

3. If the length of a cable is doubled the insulation resistance will be:

a. quartered

b. halved

c. remain the same

d. doubled.

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

4. If the length of a cable is doubled the resistance will be:

a. quartered

b. halved

c. remain the same

d. doubled.

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

5. When carrying out an initial verification, a check for polarity is carried out when energising of the installation for the first time. This is to confirm:

a. correct connection of the incoming supply

b. correct connection of equipment

c. operation of the main isolator

d. operation of the supply fuse.

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

6. A continuity of protective conductors test is carried out using a:

a. continuity tester

b. low reading ohmmeter

c. low resistance ohmmeter

d. insulation tester.

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

7. An increase in conductor operating temperature will result in:

a. an decrease in conductor resistance

b. an increase in conductor resistance

c. an increase in insulation resistance

d. no apparent change in resistance or insulation resistance.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?