Inspection and Testing Sample questions

Inspection and Testing Sample questions

1st - 12th Grade

20 Qs

quiz-placeholder

Similar activities

7th Grade PLTW Electronics Key Term Quiz

7th Grade PLTW Electronics Key Term Quiz

7th Grade

20 Qs

1CIEL - Evaluation fin de semestre 1

1CIEL - Evaluation fin de semestre 1

2nd Grade

20 Qs

Occupational Health & safety

Occupational Health & safety

10th Grade

20 Qs

1 - les bases théoriques de l'électricité

1 - les bases théoriques de l'électricité

1st Grade

16 Qs

Electric/Solar Green Cars

Electric/Solar Green Cars

7th - 8th Grade

21 Qs

Les Schémas de liaison à la terre

Les Schémas de liaison à la terre

1st Grade

21 Qs

Senior Weekly Quiz 12/18/2020

Senior Weekly Quiz 12/18/2020

11th - 12th Grade

20 Qs

Ham Radio Extra Questions Till 2020 Set E5C

Ham Radio Extra Questions Till 2020 Set E5C

KG - Professional Development

17 Qs

Inspection and Testing Sample questions

Inspection and Testing Sample questions

Assessment

Quiz

Specialty

1st - 12th Grade

Medium

Created by

Chris Falet

Used 144+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

1. The non-statutory document that is applicable to the probes and leads of test equipment is:

a. HSE Guidance Note GS 38

b. BS7671

c. The IET On Site Guide

d. IET Guidance Note 3.

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The following tests may be carried out on a new installation:

1. polarity

2. insulation resistance

3. ring final circuit continuity

4. cpc continuity.

The relevant test in the correct sequence for a new ring final circuit are:

a. 2,1,4

b. 1,2,4,3

c. 3,1,2

d. 3,2,1.

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

3. If the length of a cable is doubled the insulation resistance will be:

a. quartered

b. halved

c. remain the same

d. doubled.

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

4. If the length of a cable is doubled the resistance will be:

a. quartered

b. halved

c. remain the same

d. doubled.

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

5. When carrying out an initial verification, a check for polarity is carried out when energising of the installation for the first time. This is to confirm:

a. correct connection of the incoming supply

b. correct connection of equipment

c. operation of the main isolator

d. operation of the supply fuse.

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

6. A continuity of protective conductors test is carried out using a:

a. continuity tester

b. low reading ohmmeter

c. low resistance ohmmeter

d. insulation tester.

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

7. An increase in conductor operating temperature will result in:

a. an decrease in conductor resistance

b. an increase in conductor resistance

c. an increase in insulation resistance

d. no apparent change in resistance or insulation resistance.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?