SAT APPS

SAT APPS

Professional Development

7 Qs

quiz-placeholder

Similar activities

Agile Fundamentals - Spini

Agile Fundamentals - Spini

Professional Development

12 Qs

Agile Quiz - Aug 2022

Agile Quiz - Aug 2022

Professional Development

10 Qs

Agile Project Management

Agile Project Management

Professional Development

10 Qs

Day 3 Class Quiz

Day 3 Class Quiz

Professional Development

10 Qs

PreTest - Scrum Quiz

PreTest - Scrum Quiz

Professional Development

10 Qs

Agile Product/ Project Management Quiz

Agile Product/ Project Management Quiz

Professional Development

12 Qs

ASP-SM-Art

ASP-SM-Art

Professional Development

8 Qs

Scrum Quiz

Scrum Quiz

Professional Development

10 Qs

SAT APPS

SAT APPS

Assessment

Quiz

Professional Development, Computers

Professional Development

Easy

Created by

Divya Chauhan

Used 4+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What is the purpose of Daily Scrum? (Select 3)

Raise blockers

Detailed explanations of work done which must take more than 15 mins each

Quick and concise update on "what you did yesterday".

Finger pointing and blaming others.

Updated on "what you will do today"

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following meetings is not part of Scrum?

Product review meeting

Sprint review meeting

Sprint planning meeting

Sprint retrospective meeting

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A burn-down chart shows -

The declining energy level of the team

The progress of the work and features completed

The number of hours worked after dark

The rate of reduction of budget for a project

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In an Agile environment, what is the main responsibility of a tester?

Create test scenarios and test cases

Finding bugs

Create automation scripts

Send test execution reports to the stakeholders

There is no role as a Tester in Scrum

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Scrum, when is a Sprint Over?

When all the Sprint Backlog Items are completed

When the Product Owner suggests

When the developers dont want to work anymore

When the final testing is completed

When the time box expires

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is delivered at the end of the Sprint?

A document containing test cases for the current sprint

An architectural design of the solution

An increment of Done software

Wireframes designs for User Interface

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The reason for holding regular retrospectives is …

It allows the team to take a welcome break from work

It gives management information to use in performance reviews

It allows learning that can be used to improve team performance

It prevents deviation from the process the team has been following