Scrum-Agile Quiz # 2
Quiz
•
Professional Development, Business
•
Professional Development
•
Practice Problem
•
Hard
Tairi Mobley
Used 8+ times
FREE Resource
Enhance your content in a minute
42 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Scrum Events: Only the Product Owner and the Development Team participate in the Sprint Planning. There is nothing to do for the Scrum Master.
True
False
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Scrum Events: Could the Sprint Planning be finished if only work planned for the first days of the Sprint is decomposed to units of one day or less?
Yes, if the remaining work is also estimated, maybe in bigger units
No, all items in the Sprint Backlog should be decomposed to units of one day or less by the end of the Sprint Planning
3.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Scrum Team: How does the Scrum Master help the Product Owner? Select the three most appropriate answers.
Introducing cutting edge development practices
Facilitating Scrum events as requested or needed
Leading and coaching the organization in its Scrum adoption
Finding techniques for effective Product Backlog management
Understanding product planning in an empirical environment
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Scrum Events: What is the input to the Sprint Planning? Select four.
The Product Backlog
Projected capacity of the Development Team during the Sprint
Feedback from the Key Stakeholders
The latest product Increment
Past performance of the Development Team
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Scrum Team: Could the Product Owner and the Scrum Master be a part of the Development Team?
Yes- Scrum does not prohibit the Product Owner or the Scrum Master do development work.
No- it is not the best practice because it could create a conflict of interest.
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Scrum Team: What does Product Backlog management include? Select three most applicable items.
Presenting Product Backlog items to the Key Stakeholders
Ordering the items in the Product Backlog to best achieve goals and missions
Ensuring that the Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next
Moving Product Backlog items into the Sprint Backlog
Optimizing the value of the work the Development Team performs
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Scrum Events: Other people than the Scrum Team can attend the Sprint Planning in order to provide technical or domain advice.
True
False
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
39 questions
Test Training House 1st Season Rudy Patch
Quiz
•
Professional Development
40 questions
SEQUAL-SIM EXAM 1:CERTIFICATE IN PROFESSIONAL SCRUM PRACTICE
Quiz
•
Professional Development
40 questions
Certified Information Systems Security Professional (CISSP)
Quiz
•
Professional Development
44 questions
LV2.2Q imi revision
Quiz
•
Professional Development
40 questions
NRF Customer Service & Sales Chp. 3 Review
Quiz
•
Professional Development
40 questions
Central Heating 6035-02 | Part 3
Quiz
•
Professional Development
37 questions
M3 uf1 Nf2 Magnituds i dosimetria
Quiz
•
Professional Development
47 questions
IMI auto LV08 Chassis Diagnotics
Quiz
•
Professional Development
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade