APQP Training - VP Event - Part 1

APQP Training - VP Event - Part 1

Professional Development

11 Qs

quiz-placeholder

Similar activities

Problem Solving 3.0

Problem Solving 3.0

Professional Development

10 Qs

ออสซิโลสโคป

ออสซิโลสโคป

KG - Professional Development

12 Qs

NGOBAR ABG - DIGITAL SAVVY - SESI 1

NGOBAR ABG - DIGITAL SAVVY - SESI 1

KG - Professional Development

10 Qs

EVH deel 4

EVH deel 4

Professional Development

13 Qs

Salesforce App Builder Certification Prep

Salesforce App Builder Certification Prep

10th Grade - Professional Development

10 Qs

VM POP QUIZ!

VM POP QUIZ!

Professional Development

10 Qs

Inventory Vocabulary

Inventory Vocabulary

Professional Development

7 Qs

Quiz New Business Process

Quiz New Business Process

Professional Development

10 Qs

APQP Training - VP Event - Part 1

APQP Training - VP Event - Part 1

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Josue Galvan

Used 7+ times

FREE Resource

11 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What are the Vehicle Prototype (VP) requirements?, select all applicable.

Confirmation of Tool Readiness

Parts produced from hard tools

SCA stage 1 conducted

DCP confirmed

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Parts PO will be released and received before VP build

True

False

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is not a Technical Documentation?

SC-CC / Consequence class defined

Material Specification

DCP

Technical Regulations (TR)

Drawing and Measuring Point (MP) Drawing ready

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The objective with the Dimensional Control Plan is to analyze capability during pre-production and to secure capability in running production

True

False

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Gauges should be ready and available to measure parts for delivery to VP MRD

True

False

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Dimensional study should be performed with serial tooling by VP event

True

False

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Suppliers should have CM4D software installed

True

False

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?