1. You gave the responsibility of collecting requirement from project stakeholder to four of your team members. After starting the requirement collection process, one of your team members left the job and the requirements could not be compiled properly. Initially, you did not notice this, however, during a product review, a few stakeholders told you that some of the features in the product were not requested by them. Therefore, to verify their comments you review the product requirements and identify the issue.
PMP Exam Preparation Mentoring Ch 5 Project Scope Management

Quiz
•
Education
•
KG
•
Hard
quiz eNetwoQ
Used 18+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A. Scope creep
B. Scope slippage
C. Gold Scope
D. Opportunity
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3. The client informs you that he noticed some parts of the work are not being completed by your team. You ensure him that you will look into it and give a proper response after verifying the facts.
Which document will you refer to verify it?
A. Project scope statement
B. WBS dictionary
C. Schedule baseline
D. WBS
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
4. - As the project manager for a large, complex project, you have been getting complaints from your team, including some of the management team, about all the time being spent on planning. You know that by spending time following the appropriate planning process, you can prevent many problems during execution. This will save time in the later stages of the project. One of the primary complaints you were hearing is related to the time it takes to create the Work Breakdown Structure (WBS). You are explaining the importance of the WBS to your project team members. Which of the following statements about the WBS is incorrect?
A. it is a hierarchical decomposition of Project work<br />
B. Planned work contained in the lowest level WBS components are called WBS dictionaries.<br />
C. The WBS subdivides the project work into smaller, more manageable pieces of work
D. The WBS organizes and defines the total scope of the project work
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
5. While finalizing the WBS, you assign each work package to a control account and establish a unique identified for the same work from a code of account. These identifiers help you find a hierarchical sum of costs, schedule, etc. Which statement is true about the WBS?
A. It contains all project work
B. It authorizes the project manager
C. It is a hierarchy of project staft
D. It is a hierarchical breakdown of project resources
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
6. During the collect requirement process, an influential stakeholder requested a Feature which was rejected. During the project execution, you notice that you have an opportunity to incorporate the requirement of this stakeholder into product and it will cost you nothing. By doing so, the stakeholder will be pleased and may help you in your next assignment. This is an example of:
A. Scope creep
B. Scope slippage
C. Gold plating
D. Opportunity
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
7. - In the the create WBS process, you sub-divide project deliverables and project work into smaller and more manageable components. The output of this process is the Scope Baseline and Project document updates.
Which of the following truly represents the scope baseline?
A. Scope statement, Scope management plan, Schedule baseline
B. Scope statement, WBS, WBS dictionary
C. WBS, WBS dictionary, Risk Register
D. Scope statement, WBS, Schedule baseline
Create a free account and access millions of resources
Similar Resources on Quizizz
9 questions
Corporate Finance in Project Management - 22/11/2024

Quiz
•
University
10 questions
ABSTRACT WRITING

Quiz
•
Professional Development
11 questions
Research Objectives & Research Background

Quiz
•
University
10 questions
PMP ExamStudy Group - Project Cost Management

Quiz
•
KG
10 questions
EYE CURRICULUM

Quiz
•
Professional Development
10 questions
I LOVE ANIMAL,I CARE FOR ANIMALS

Quiz
•
KG
14 questions
Project Supervision and Coordination Quiz

Quiz
•
12th Grade
10 questions
Research

Quiz
•
10th - 12th Grade
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade
Discover more resources for Education
10 questions
Identifying equations

Quiz
•
KG - University
15 questions
Music 2016

Quiz
•
KG - 12th Grade
44 questions
logos

Quiz
•
KG - University
20 questions
Disney Characters

Quiz
•
KG
20 questions
Kids shows

Quiz
•
KG
20 questions
Guess that Disney

Quiz
•
KG - 5th Grade
20 questions
Cartoon Characters!

Quiz
•
KG - 5th Grade