PMP Exam Mentoring Ch 8 Project Quality Management

PMP Exam Mentoring Ch 8 Project Quality Management

KG

10 Qs

quiz-placeholder

Similar activities

About Intelligence

About Intelligence

12th Grade

10 Qs

PMP Exam Preparation - Ch 12 Project Procurement Management

PMP Exam Preparation - Ch 12 Project Procurement Management

KG

10 Qs

LO1 OB

LO1 OB

University

10 Qs

24-25 PMR Stakeholders Review

24-25 PMR Stakeholders Review

9th Grade

15 Qs

PMP Exam Preparation-eNetwoQ Ch 11 Project Risk Management

PMP Exam Preparation-eNetwoQ Ch 11 Project Risk Management

KG

10 Qs

PMP Exam Preparation Mentoring Ch 5 Project Scope Management

PMP Exam Preparation Mentoring Ch 5 Project Scope Management

KG

10 Qs

PMP ExamStudy Group - Project Cost Management

PMP ExamStudy Group - Project Cost Management

KG

10 Qs

Leader vs Boss

Leader vs Boss

1st Grade

10 Qs

PMP Exam Mentoring Ch 8 Project Quality Management

PMP Exam Mentoring Ch 8 Project Quality Management

Assessment

Quiz

Education

KG

Medium

Created by

quiz eNetwoQ

Used 19+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

1. At the sprint planning meeting, the scrum master reiterates that if by the end of the sprint the product increment that the agile project team is building does not meet the criteria specified at the beginning of the sprint, this work will not be included in the velocity for the current sprint.

What does the scrum master refer to?

A. Estimate to complete

B. Definition of done

C. Project exit criteria

D. Quality metrics

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

2. As part of the quality assurance efforts, the project team identifies that several deliverables do not conform with the quality requirements.

What should the team do next?

A. Perform the Plan Quality Management process

B. Review the quality management plan to determine what to do with the nonconforming products

C. Document the findings and repair the deliverables

D. Review the risk report to gain guidance on what corrective action should be implemented

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

3. As part of project planning, you review the lessons learned repository. You notice that although most of the projectmanagement processes have been properly performed on all of the past projects, the quality of deliverables was far frombeing perfect. You want to ensure that your project delivers better results and that quality issues are detected early in the project life cycle.

What can you do to achieve your goal?

A. Estimate costs more accurately

B. Validate scope on a daily basis

C. Conduct recurring retrospectives

D. Hire an external quality vendor

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

4. Your project team is in the process of implementing the activities specified in the quality management plan. The scope, schedule, and budget are clear and well defined. Therefore, you manage this project using predictive methods. However,since your next project is agile, you want to start experimenting with some agile practices already in your current project.

What can you do to achieve your goal as part of the process performed by the team?

A. Suggest that the team use alternative analysis instead of document analysis

B. Encourage continuous stakeholder engagement with the team members

C. Incorporate team-building activities into product testing and inspection tasks

D. Limit stakeholder involvement to shield the team from external distractions

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

5. The project you are leading has a current CPI of 1.0 and SPI of 0.8. You have been notified by the project management office that your project has been selected for a quality audit that is scheduled to take place over the coming weeks.

What should be your primary concern with regards to the audit?

A. That the project falls back in line with the project schedule

B. Finding errors, defects, bugs, or other nonconformance problems in the product

C. Assuring that the project products fall within the sponsor's acceptance limits

D. That the work performed lines up with company policies, processes, and procedures

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

6. A project manager working on a phone development project has met with the project team to determine the grade and quality of the product. The phone needs to have just basic functionality to be sold in emerging markets. What should the quality and grade be for the project?

A. High Quality, Low Grade

B. Low Quality, High Cost

C. Low Quality, Easy Maintenance

D. Low Quality, High Grade

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

7. As part of the process to develop the quality management plan, the project manager establishes the roles and responsibilities for the quality of the deliverables. The project manager decides that quality management will be performed by all team members throughout the project rather than being the responsibility of specific team members at the end of the project.

What is the project manager trying to achieve in this scenario?

A. Incorporating traditional quality management practices into an agile project

B. Avoiding responsibility in case the deliverables do not meet quality specifications

C. Determining the areas of strengths and weaknesses of the team members

D. Incorporating agile quality management practices into a traditionally lead project

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?