First Exam

Authored by Wilson Torres

Professional Development

1st - 5th Grade

Used 1+ times

First Exam
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Pedro is analyzing with his team, the impact of some variables including risks and concludes that the levels are high At what stage of the project are you?

Definition

Planning

Start

monitoring and definition

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is incorrect about stakeholder management?

Stakeholders are in the environment, not within the organization

It requires interpersonal skills

There are no incorrect answer options

Stakeholders are a key source of information for defining scope.

The promoters and detractors of the project should be identified

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Innovative or has sufficient market, articulated with the business strategy, It has an irrefutable legal justification or attend to an urgency are characteristic of:

Project

None of the options is correct

Project Idea

Project Plan

Logic Framework

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Why it is important to involve stakeholders in the various project processes?

Serves for effective communication

Determine the scope restrictions

Avoid scope changes

All the answers are correct

Improve the probability of having a satisfied customer

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

It has been identified that the project manager's leadership is the main problem of project failure, It ARE NOT signs of this situation are:

Poor productivity

Bad relations into the team

All the options are correct

cost overruns

Lack of motivation

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Pedro is analyzing with his team, the impact of some variables including risks and concludes that the levels are high At what stage of the project are you?

Start

Ideation

Identification and monitoring

Planning

Definition

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Operations and projects have similar characteristics except:

They must be properly planned

They have limited resources

They are repetitive processes

They are followed up

They seek organizational objectives

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?