
CAPM Test - Project Schedule and Cost Management
Authored by quiz eNetwoQ
Professional Development
KG
Used 13+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
1. Which of the following is the full and correctly ordered list of processes in the Project Schedule Management Knowledge Area?
A. Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule
B. Define Activities, Estimate Activity Durations, Sequence Activities, Develop Schedule, Control Schedule
C. Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule
D. Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Control Schedule, Develop Schedule
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2. The Scope baseline is an input to what process in Schedule Management?
A. The Scope baseline is an input to Plan Schedule Management
B. The Scope baseline is an input to Define Activities
C. The Scope baseline is an input to Estimate Activity Resource Requirements
C. The Scope baseline is an input to Estimate Activity Resource Requirements
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3. Which of the following are outputs of Define Activities?
A. Sequenced activities
B. Milestone chart
C. Activity attributions
D. None of the above
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4. Which of the following are outputs of Define Activities?
A. Activity list
B. Milestone list
C. Activity attributes
D. All of the above
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5. Planning is underway for a new feature to be built at an aquarium in Atlanta Georgia. The activities for this phase have all been defined within the WBS. What process will be performed next?
A. Estimate Activity Durations
B. Define Activities
C. Estimate Costs
D. Sequence Activities
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
6. Costs are being estimated a new project. Funding limits will be set based on these cost estimates, and if they're too low, it could cause serious delays and adverse management attention. What type of estimating will be most appropriate and why?
A. Analogous estimating because this will capture previous project experience.
B. Parametric estimating because nearly 80 percent of project cost is concrete, which has a predictable cost per square foot.
C. Bottom-up estimating, because this will be most thorough
D. Top-down estimating because the estimates need to be aligned with historical costs.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7. Which of the following is an accurate description of the Cost baseline?
A. The cost baseline is compared against plan to calculate cost variances and CPI
B. The cost baseline is an output of Determine Budget, is subject to formal change control and does not include any management reserves
C. The Cost baseline is an input to Determine Budget
D. The Cost baseline is an output of Determine Budget, and includes contingency and management reserves
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?