
EV Management
Authored by Malak Attia
Business
University
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The first step in the project control process for measuring and evaluating project performance is to
set a baseline plan
determine the project objectives.
determine the project deliverables
analyze the project budget
analyze the project budget
Answer explanation
The project control steps for measuring and evaluating project performance are first to set a baseline plan, then to measure progress and performance, next to compare plan against actual and finally taking action
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion(CPI)
the project will currently finish under budget, assuming the project continues to perform in this way.
the project will currently finish over budget, assuming the project continues to perform in this way.
the project will currently finish on budget, assuming the project continues to perform in this way.
the project will currently finish behind schedule, assuming the project continues to perform in this way.
there is insufficient information to draw conclusions.
Answer explanation
Since the EV is greater than the AC, at this time, the project is expected to finish under budget
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The second step in the project control process for measuring and evaluating project performance is to
review the baseline plan with top management
analyze inputs to control system
compare plan against actual
measure progress and performance
review spending with team members.
Answer explanation
The project control steps for measuring and evaluating project performance are first to set a baseline plan, then to measure progress and performance, next to compare plan against actual and finally taking action
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A team leader tells the project manager that as of right now, $1.20 worth of work has been accomplished for each $1 worth of scheduled work. The team leader got this information from viewing the
SV
TCPI
CPI
SPI
PCIB
Answer explanation
•An SPI of 1.2 would tell the team leader that $1.20 worth of work has been accomplished for each $1 worth of scheduled work.
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The earned value of a project is the
project cost to date adjusted for project scope changes.
total project cost to date.
cost incurred minus the planned cost.
estimated cost that has been earned by work that is completed
the planned time-phased baseline of the value of work scheduled
Answer explanation
•Earned value for a task is simply the percent complete multiplied by the original budget. Stated differently, EV is the percent of the original budget that has been earned by actual work completed.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?