EV Management
Quiz
•
Business
•
University
•
Practice Problem
•
Hard
Malak Attia
Used 2+ times
FREE Resource
Enhance your content in a minute
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The first step in the project control process for measuring and evaluating project performance is to
set a baseline plan
determine the project objectives.
determine the project deliverables
analyze the project budget
analyze the project budget
Answer explanation
The project control steps for measuring and evaluating project performance are first to set a baseline plan, then to measure progress and performance, next to compare plan against actual and finally taking action
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion(CPI)
the project will currently finish under budget, assuming the project continues to perform in this way.
the project will currently finish over budget, assuming the project continues to perform in this way.
the project will currently finish on budget, assuming the project continues to perform in this way.
the project will currently finish behind schedule, assuming the project continues to perform in this way.
there is insufficient information to draw conclusions.
Answer explanation
Since the EV is greater than the AC, at this time, the project is expected to finish under budget
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The second step in the project control process for measuring and evaluating project performance is to
review the baseline plan with top management
analyze inputs to control system
compare plan against actual
measure progress and performance
review spending with team members.
Answer explanation
The project control steps for measuring and evaluating project performance are first to set a baseline plan, then to measure progress and performance, next to compare plan against actual and finally taking action
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A team leader tells the project manager that as of right now, $1.20 worth of work has been accomplished for each $1 worth of scheduled work. The team leader got this information from viewing the
SV
TCPI
CPI
SPI
PCIB
Answer explanation
•An SPI of 1.2 would tell the team leader that $1.20 worth of work has been accomplished for each $1 worth of scheduled work.
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The earned value of a project is the
project cost to date adjusted for project scope changes.
total project cost to date.
cost incurred minus the planned cost.
estimated cost that has been earned by work that is completed
the planned time-phased baseline of the value of work scheduled
Answer explanation
•Earned value for a task is simply the percent complete multiplied by the original budget. Stated differently, EV is the percent of the original budget that has been earned by actual work completed.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
8 questions
Business Vision and Mission
Quiz
•
University
10 questions
MGT315-CH 1
Quiz
•
University
10 questions
internships
Quiz
•
University - Professi...
10 questions
MKT243 - CHAP 1
Quiz
•
University
10 questions
MKT571_Pop Quiz_CH02
Quiz
•
University
10 questions
FO 101: Types of Accommodation
Quiz
•
University
10 questions
Public Mutual Biz
Quiz
•
1st Grade - Professio...
10 questions
Week 9 小測驗 (PAPER 3 + HBR1 & 2)
Quiz
•
University
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade
Discover more resources for Business
12 questions
IREAD Week 4 - Review
Quiz
•
3rd Grade - University
23 questions
Subject Verb Agreement
Quiz
•
9th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University
5 questions
Poetry Interpretation
Interactive video
•
4th Grade - University
19 questions
Black History Month Trivia
Quiz
•
6th Grade - Professio...
15 questions
Review1
Quiz
•
University
15 questions
Pre1
Quiz
•
University
