EV Management

EV Management

University

5 Qs

quiz-placeholder

Similar activities

FO 101: Types of Accommodation

FO 101: Types of Accommodation

University

10 Qs

Business Vision and Mission

Business Vision and Mission

University

8 Qs

MK2 - Quiz Kebijakan Hutang - Kelompok 3

MK2 - Quiz Kebijakan Hutang - Kelompok 3

University

10 Qs

internships

internships

University - Professional Development

10 Qs

CHAPTER 5 & 6

CHAPTER 5 & 6

University

10 Qs

MKT243 - CHAP 1

MKT243 - CHAP 1

University

10 Qs

K3

K3

University

10 Qs

International financing

International financing

University

10 Qs

EV Management

EV Management

Assessment

Quiz

Business

University

Practice Problem

Hard

Created by

Malak Attia

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The first step in the project control process for measuring and evaluating project performance is to

set a baseline plan

determine the project objectives.

determine the project deliverables

analyze the project budget

analyze the project budget

Answer explanation

The project control steps for measuring and evaluating project performance are first to set a baseline plan, then to measure progress and performance, next to compare plan against actual and finally taking action

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion(CPI)

the project will currently finish under budget, assuming the project continues to perform in this way.

the project will currently finish over budget, assuming the project continues to perform in this way.

the project will currently finish on budget, assuming the project continues to perform in this way.

the project will currently finish behind schedule, assuming the project continues to perform in this way.

there is insufficient information to draw conclusions.

Answer explanation

Since the EV is greater than the AC, at this time, the project is expected to finish under budget

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The second step in the project control process for measuring and evaluating project performance is to

review the baseline plan with top management

analyze inputs to control system

compare plan against actual

measure progress and performance

review spending with team members.

Answer explanation

The project control steps for measuring and evaluating project performance are first to set a baseline plan, then to measure progress and performance, next to compare plan against actual and finally taking action

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A team leader tells the project manager that as of right now, $1.20 worth of work has been accomplished for each $1 worth of scheduled work. The team leader got this information from viewing the

SV

TCPI

CPI

SPI

PCIB

Answer explanation

An SPI of 1.2 would tell the team leader that $1.20 worth of work has been accomplished for each $1 worth of scheduled work.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The earned value of a project is the

project cost to date adjusted for project scope changes.

total project cost to date.

cost incurred minus the planned cost.

estimated cost that has been earned by work that is completed

the planned time-phased baseline of the value of work scheduled

Answer explanation

Earned value for a task is simply the percent complete multiplied by the original budget. Stated differently, EV is the percent of the original budget that has been earned by actual work completed.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?