Project Controls PC 10 Rev 03
Authored by Gary Carr
Professional Development
1st Grade
Used 10+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
14 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Assumptions are forecasts about what may happen in the future, while constraints are limits on freedom of choice?
True
False
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Do Assumptions need to be monitored and validated through the use of dedicated scheduled meetings?
Depends on the size of the project
Sometimes
No
Yes
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The develop Project Charter Process has two outputs, one is the Project Charter and the other is?
Risk Register
Formal Change Request Process
Lessons Learned
Assumptions Log
None of the options listed
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Do Assumptions have a responsible person assigned specifically to each and if so why.
Assumptions are logged once and never reviewed
Assumptions are constantly validated by a responsible person
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Time, Cost, Scope & Quality are often referred to as the?
Triple Header
Triple Assumption
Triple Risk
Triple Constraint
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The main reason Risks are managed is to allow what to occur?
Plan & Macro Manage
Plan & Micro Manage
Plan & Mitigate
Plan & Process
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Determining and Evaluating Risks is also referred to as?
Possible & Issue
Probability & Impact
Issue & Effect
All options Listed
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?