PM1 Scope Review

PM1 Scope Review

9th - 12th Grade

25 Qs

quiz-placeholder

Similar activities

A2 Business Economics

A2 Business Economics

12th Grade

20 Qs

Staffing Quiz-2

Staffing Quiz-2

12th Grade

20 Qs

Marketing, Competition and costumer

Marketing, Competition and costumer

9th Grade

20 Qs

Sources of Finance

Sources of Finance

9th - 10th Grade

20 Qs

Module 6: Social Groups and Organization

Module 6: Social Groups and Organization

11th Grade - Professional Development

20 Qs

SGS Business 2.1.5 Ethics and Business

SGS Business 2.1.5 Ethics and Business

9th - 11th Grade

20 Qs

EDPM  END OF TERM EXAM

EDPM END OF TERM EXAM

12th Grade

20 Qs

Markets

Markets

12th Grade

20 Qs

PM1 Scope Review

PM1 Scope Review

Assessment

Quiz

Business

9th - 12th Grade

Hard

Created by

Bobbie Jones

Used 55+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If you are breaking a project into pieces at a meeting by decomposing it into tasks so that you can track, define and manage activities, what are you doing?

collecting requirements.

creating the WBS.

defining the scope.

verifying the scope.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Carmine is a wedding planner. He has created a WBS to subdivide a

project into more manageable tasks. To highlight the details of the event

for all vendors who are fulfilling deliverables for the wedding, he is

preparing a document that describes the cost estimates, quantity

requirements, description of the work, and contract information. Carmine

is working on the:

project scope statement.

requirements documentation.

work breakdown structure.

work breakdown structure dictionary.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Andrew is the prom committee chairman. He is on-site at the prom to

make sure all vendors show up at the event and all vendors' activities are

falling within the scope of work contracted. Which process stage is

Andrew in?

initiating

executing

monitoring and controlling

closing

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Andrew is the prom committee chairman. He is at the prom and realizes

that the meal delivered to the attendees was steak and not chicken.

Andrew makes the catering manager aware immediately that the chicken

meal was agreed upon, so the steak meal is outside the project scope.

Which project management process stage is Andrew in?

initiating

executing

monitoring and controlling

closing

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a PM has a budget of $250,000 and 10 months to finish a project, which section of the project scope statement would these components be listed?

project acceptance criteria

project constraints

project deliverables

project exclusions

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Delores is leading a marketing project. She meets with the stakeholders

to define and document all the needs for the marketing project. The

activity that Delores is participating in is referred to as:

collecting requirements.

controlling the scope.

creating the WBS.

verifying the scope.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As a PM you must determine how to handle change requests. When you are determining the process that will be used, what are you conducting?

collect requirements

control scope

define scope

verify scope.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?