1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If you are breaking a project into pieces at a meeting by decomposing it into tasks so that you can track, define and manage activities, what are you doing?
collecting requirements.
creating the WBS.
defining the scope.
verifying the scope.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Carmine is a wedding planner. He has created a WBS to subdivide a
project into more manageable tasks. To highlight the details of the event
for all vendors who are fulfilling deliverables for the wedding, he is
preparing a document that describes the cost estimates, quantity
requirements, description of the work, and contract information. Carmine
is working on the:
project scope statement.
requirements documentation.
work breakdown structure.
work breakdown structure dictionary.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Andrew is the prom committee chairman. He is on-site at the prom to
make sure all vendors show up at the event and all vendors' activities are
falling within the scope of work contracted. Which process stage is
Andrew in?
initiating
executing
monitoring and controlling
closing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Andrew is the prom committee chairman. He is at the prom and realizes
that the meal delivered to the attendees was steak and not chicken.
Andrew makes the catering manager aware immediately that the chicken
meal was agreed upon, so the steak meal is outside the project scope.
Which project management process stage is Andrew in?
initiating
executing
monitoring and controlling
closing
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If a PM has a budget of $250,000 and 10 months to finish a project, which section of the project scope statement would these components be listed?
project acceptance criteria
project constraints
project deliverables
project exclusions
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Delores is leading a marketing project. She meets with the stakeholders
to define and document all the needs for the marketing project. The
activity that Delores is participating in is referred to as:
collecting requirements.
controlling the scope.
creating the WBS.
verifying the scope.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
As a PM you must determine how to handle change requests. When you are determining the process that will be used, what are you conducting?
collect requirements
control scope
define scope
verify scope.
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
BM I Unit 1.06

Quiz
•
9th Grade
20 questions
Lean Six Sigma - Intro & Define Chapters

Quiz
•
7th - 10th Grade
25 questions
PMI practice 2

Quiz
•
9th Grade
30 questions
Project Management Quiz

Quiz
•
10th Grade
21 questions
PM2 Unit 4 Review (PMI)

Quiz
•
9th - 12th Grade
20 questions
Project Mgmt. I Final Review 1 21-22

Quiz
•
9th - 12th Grade
23 questions
CIW Review

Quiz
•
9th - 12th Grade
20 questions
RO93 - 2.2 - Client requirements and how they are defined

Quiz
•
10th Grade
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade
Discover more resources for Business
50 questions
Trivia 7/25

Quiz
•
12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade
6 questions
RL.10.1 Cite Evidence

Quiz
•
10th Grade
10 questions
Characteristics of Life

Quiz
•
9th - 10th Grade
14 questions
Algebra 1 SOL Review #1

Quiz
•
9th Grade