PMBoK - PROCUREMENT

PMBoK - PROCUREMENT

1st - 12th Grade

7 Qs

quiz-placeholder

Similar activities

2/26/2018

2/26/2018

1st - 10th Grade

10 Qs

国际贸易术语

国际贸易术语

1st - 3rd Grade

3 Qs

PMP Scenario-Based Questions

PMP Scenario-Based Questions

4th Grade

10 Qs

training 8 aug ciast - muhaimin

training 8 aug ciast - muhaimin

1st - 5th Grade

10 Qs

Freight Forwarding Phase 1

Freight Forwarding Phase 1

1st - 3rd Grade

10 Qs

Mixed Bank 5

Mixed Bank 5

9th Grade - Professional Development

10 Qs

Work Readiness Quiz

Work Readiness Quiz

9th - 10th Grade

11 Qs

Pengantar Trade

Pengantar Trade

1st - 3rd Grade

10 Qs

PMBoK - PROCUREMENT

PMBoK - PROCUREMENT

Assessment

Quiz

Professional Development

1st - 12th Grade

Hard

Created by

Andi Nirmala

Used 7+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which process of Project Procurement Management is in executing process group?

Plan Procurement

Conduct Procurement

Control Procurement

Close Procurement

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is not includes as type of contract?

Fixed price

Centralized contract

Cost reimbursable

Time and materials

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which contract use when the project is small and scope is not clearly definied?

Fixed price

Cost plus incentive fee

Cost plus award fee

Time and materials

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which process obtains seller responses, select seller and awarding contract?

Plan Procurement

Conduct Procurement

Control Procurement

Bidder Conference

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In seller perspective, which one of this type of contract that has the highest risk?

Firm fixed price

Time and material

Cost plus fee

Fixed price economic price adjusment

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In buyer perspective, which one of this type of contract that has the highest risk?

Firm fixed price

Time and material

Cost plus fee

Fixed price economic price adjusment

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following is NOT the output of conduct procurement?

Selected seller

Agreements

Make or buy decision

Change request