IPMAC_PMP_L08P_Integration Management

IPMAC_PMP_L08P_Integration Management

Professional Development

11 Qs

quiz-placeholder

Similar activities

Term 1 Reflection

Term 1 Reflection

KG - Professional Development

11 Qs

Interpersonal Skills

Interpersonal Skills

Professional Development

11 Qs

Repair Quiz

Repair Quiz

Professional Development

15 Qs

post Test English Camp 2

post Test English Camp 2

Professional Development

10 Qs

Link & ( Super ) Match

Link & ( Super ) Match

Professional Development

10 Qs

#SQC2022INNOCREATIVATION

#SQC2022INNOCREATIVATION

Professional Development

16 Qs

HFTSK-Disbursements_Jul2024_Part2

HFTSK-Disbursements_Jul2024_Part2

Professional Development

8 Qs

INTO Artificial Intelligence

INTO Artificial Intelligence

University - Professional Development

10 Qs

IPMAC_PMP_L08P_Integration Management

IPMAC_PMP_L08P_Integration Management

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Giang Vien

Used 3+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following sets of processes will you expect to see in the Project Integration Knowledge Area?

Collect Requirements, Define Scope, Estimate Activity Durations

Define Scope, Create the WBS, Perform Integrated Change Control

Develop Project Charter, Develop Project Management Plan, Close Project or Phase

Define activities, Sequence activities, Develop Schedule

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The Director (Information Systems) in your company is in the process of creating a project charter to formally authorize a new project in your company. In this context, what should she do FIRST?

Review the preliminary project scope statement

Identify a project manager for the project

Use earned value technique

Integrate the work of the project with the ongoing operations of the performing organization.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In a recent job interview, you were asked to define the most important characteristic of a project manager. A good answer will be:

Subject Matter Expert

Integrator

Creative person

Risk minimizer

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The following are the key benefits of the Develop Project Charter process EXCEPT:

It provides a direct link between the project and the strategic objectives of the organization.

It creates a formal record of the project.

It defines the product, service or result boundaries, and acceptance criteria.

It shows the organizational commitment to the project

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The latest change request you received does not impact the project cost. As a Project Manager, what should be your next step?

Speak to your Manager about the Change Request

Send the Change Request to the Change Control Board (CCB)

Evaluate the impact on other project constraints

Go ahead and make the change

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is most important when it comes to change from Project Manager’s perspective?

Inform the sponsor about the change

Record and track the progress of the change

Avoid the change

Prevent uncontrolled change

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

As a Project Manager, you know you need to manage the stakeholders. Your new project is with a customer who is famous for requesting changes. Grapevine has it that the previous Project Manager was totally frustrated with this customer and moved to a different department. With this new project kicking off, what would you do to manage this customer?

Send the customer a copy of the organization’s change control process

Speak with the manager of this customer and discuss how the previous Project Manager has left after getting frustrated from the requested changes

Involve the customer as early in the project as possible

Deny a couple of changes firmly

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?