
iPMAC_PMP_L08P_Schedule Management and Cost Management
Quiz
•
Professional Development
•
Professional Development
•
Practice Problem
•
Medium
Giang Vien
Used 5+ times
FREE Resource
Enhance your content in a minute
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager overseeing the construction of a Baseball Stadium. The activity of laying the Grass Sod has an optimistic estimate of 10 days, pessimistic estimate of 16 days, and most likely estimate of 13 days. What is the duration within which this task must be completed?
10 days to 16 days
7 days to 19 days
12 days to 14 days
11 days to 15 days
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
There are two activities on your schedule, which are: 1) Install server in lab 2) Move server into the data center. However, the second task can’t start until the server has run in the lab for 5 days without failure. This is an example of what?
Fast Track
Lead
Crashing
Lag
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
In a Finish to Start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity 5 days before its predecessor is complete. This is accomplished by providing 5 days of:
Lag
Load
Fast-tracking
Lead
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your project schedule shows a 15 month finish, but your customer has just realized there is a regulatory requirement to complete the project by a certain date and insists this project must be finished in 12 months. Which of the following is the best approach?
Tell the customer it can be done, then cut your estimates by 20%.
Cut the scope by 20%, tell the customer the critical path has changed, and resubmit the schedule for review.
Stand your ground. Cutting scope or time will result in an inferior project outcome.
Inform the customer of the impacts, then crash the project.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The Cost Performance Index (CPI) of a project is 0.8 and you have a limited budget. You are planning to procure a product from the supplier. In this situation, you should:
Ask the supplier to supply a product of slightly lower quality, since it will cost less.
Try innovative means to lower costs.
Remove non-critical tasks from the project schedule.
Try to crash the project as shortening the project schedule decreases costs.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What are the 2 estimation methods that take the most time and the least time?
Expert judgement, Three point estimate
Analog, Expert judgement
Bottom up, Analog
Analog, Parametric
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project uses rounding of activity estimates data to the nearest $100, uses staff hours as the unit of measure for resources, and has a variance threshold of 10% deviation from the baseline plan. These would be typically documented in the:
Cost management plan
Scope Statement
WBS
Project charter
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
15 questions
Marketing and Advertising
Quiz
•
Professional Development
15 questions
BIR RDO 27 Caloocan Transfer Tax on Estate and Donation
Quiz
•
University - Professi...
10 questions
Assessment
Quiz
•
Professional Development
10 questions
TC Territory Management
Quiz
•
Professional Development
9 questions
5S
Quiz
•
Professional Development
10 questions
SI Units
Quiz
•
Professional Development
12 questions
Perform Online Collaboration A
Quiz
•
Professional Development
12 questions
Supersonic Space Trivia
Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Forest Self-Management
Lesson
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
30 questions
Thanksgiving Trivia
Quiz
•
9th - 12th Grade
30 questions
Thanksgiving Trivia
Quiz
•
6th Grade
11 questions
Would You Rather - Thanksgiving
Lesson
•
KG - 12th Grade
48 questions
The Eagle Way
Quiz
•
6th Grade
10 questions
Identifying equations
Quiz
•
KG - University
10 questions
Thanksgiving
Lesson
•
5th - 7th Grade
