SAFe for Teams Quiz 2 (Sections 3 and 4)
Authored by Clint Compton
Professional Development
Professional Development
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
8 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 5 pts
What is the benefit of separating release elements from the Solution?
It allows Agile Teams to launch untested Features
It allows the release of different Solution elements at different times
It allows the Agile Release Train to demo value every two weeks
It allows the Systems Team to integrate with ease
2.
MULTIPLE CHOICE QUESTION
30 sec • 5 pts
An Agile Team collects the Iteration Metrics they have agreed upon during which part of the iteration retrospective?
During the Features agreement part of the retrospective
During the quantitative part of the iteration retrospective
During the qualitative part of the iteration retrospective
During the outcome review part of the retrospective
3.
MULTIPLE CHOICE QUESTION
30 sec • 5 pts
Which factor helps unlock the intrinsic motivation of knowledge workers?
Team performance incentives
Parallel development
Pay-for-performance
Autonomy
4.
MULTIPLE CHOICE QUESTION
30 sec • 5 pts
Why do Lean-Agile leaders try to connect the silos of business, system engineering, hardware, software, test, and quality assurance?
To optimize vertical communication
To enforce organizational boundaries between functions
To align around value
To allow for friction between the teams
5.
MULTIPLE CHOICE QUESTION
30 sec • 5 pts
Which statement is true about the PI Planning event?
It involves program Portfolio Management to prioritize the Stories presented by teams during the final plan review
It involves everyone in the program over a two-day period
It involves Product Management and Product Owners on the first day and the rest of the teams on the second day
It involves only the team members who are most qualified to estimate the work
6.
MULTIPLE CHOICE QUESTION
30 sec • 5 pts
Which statement describes a cadence-based PI Planning event?
It is very important and should be postponed until all participants can attend
It is an all-hands, two-day event with the goal to create alignment
As many team members as possible should attend remotely to reduce travel costs
It is not a required event but tasks move forward at higher velocity when the meeting occurs
7.
MULTIPLE CHOICE QUESTION
30 sec • 5 pts
What is an example of a modified Fibonacci sequence?
...1, 3, 5, 9, 11, 13...
...1, 2, 4, 8, 16, 32...
...3, 5, 8, 13, 20, 40...
...3, 6, 9, 12, 15, 18...
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?