2018 Plumbing License Exam 3

2018 Plumbing License Exam 3

Professional Development

85 Qs

quiz-placeholder

Similar activities

SEO-SEM

SEO-SEM

Professional Development

81 Qs

TO PENATA LAYANAN OP

TO PENATA LAYANAN OP

Professional Development

90 Qs

True gamer

True gamer

KG - Professional Development

80 Qs

Management: Exam #1 Review

Management: Exam #1 Review

Professional Development

80 Qs

PENGETAHUAN 3 IASP 2020

PENGETAHUAN 3 IASP 2020

Professional Development

85 Qs

Cumulative Nutrition Exam

Cumulative Nutrition Exam

University - Professional Development

81 Qs

3534 - Kiến thức chung P1

3534 - Kiến thức chung P1

Professional Development

90 Qs

T3. Preparación de elaboraciones sencillas y comidas rápidas

T3. Preparación de elaboraciones sencillas y comidas rápidas

Professional Development

90 Qs

2018 Plumbing License Exam 3

2018 Plumbing License Exam 3

Assessment

Quiz

Other

Professional Development

Medium

Created by

Johnny Thulin

Used 3+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

85 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Joints between polyethylene of raised temperature (PE-RT) plastic tubing and fittings shall be joints…

heat fusion
mechanical
Solvent cemented
Threaded

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

12. The prescribed portions of standards referenced in the IPC and listed in Chapter 15 are considered __________.

a. requirements
b. guidelines
c. alternatives
d. modifications

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

25. The code official may allow temporary connection to the utility source __________.

a. pending the outcome of an appeal
b. for a period not exceeding 60 days
c. for construction purposes
d. for testing plumbing systems

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

21. Approved deck mounted vacuum breakers shall be installed with the critical level not less than __________ above the flood level of the rim.

6 inches
2 inches
One inch
Half inch

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

14. A grease interceptor is not required for the kitchen of a __________.

a. factory
b. hospital
c. school
d. dwelling unit

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

17. The minimum height of the vent termination for a flow control device on a grease interceptor is __________ inches above the flood rim of the connected fixture or as required by the manufacturer.

a. 12
b. 18
c. 6
d. 24

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

17. A 4-inch by 3-inch water closet flange is __________.

not considered a reduction in size
prohibited
an offset fitting
required

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?