RMP - 4. RISK ANALYSIS

RMP - 4. RISK ANALYSIS

1st Grade

23 Qs

quiz-placeholder

Similar activities

Day#4B: Quiz 24-25-26-27

Day#4B: Quiz 24-25-26-27

1st Grade

20 Qs

Day#2B :Quiz 10-11-12-13

Day#2B :Quiz 10-11-12-13

1st Grade

19 Qs

Project Management

Project Management

1st Grade

20 Qs

PMI SH - Evaluate and Address External Business Environment Chan

PMI SH - Evaluate and Address External Business Environment Chan

1st - 3rd Grade

24 Qs

Part 3: How to Conduct Risk Assessment & Climate

Part 3: How to Conduct Risk Assessment & Climate

1st - 5th Grade

20 Qs

CAPM-Domain#2 - Predictive, Plan-based Methodologies

CAPM-Domain#2 - Predictive, Plan-based Methodologies

1st Grade

27 Qs

ACP dari Bit.ly

ACP dari Bit.ly

1st Grade

20 Qs

Domain#5 Adaptive Planning  Mike Griffith

Domain#5 Adaptive Planning Mike Griffith

1st Grade

20 Qs

RMP - 4. RISK ANALYSIS

RMP - 4. RISK ANALYSIS

Assessment

Quiz

Professional Development

1st Grade

Easy

Created by

sudiyuwono wowo

Used 5+ times

FREE Resource

23 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Sara is the project manager for her organization. She has hired a subject matter expert to interview the project stakeholders on certain identified risks within the project. The subject matter expert will assess the risk event with what specific goal in mind:
To determine the level of probability of impact for each risk event.
To determine the validity of each risk event.
To determine the probability and cost of the risk event.
To determine the bias of the risk event based on each person interviewed.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following tools are used to identify the probability of achieving specifics cost targets?
Contingent response strategies.
Sensitivity analysis.
Monte Carlo analysis.
Decision tree analysis.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

You are the project manager of the AMD project for your organization. In this project, you are currently performing quantitative risk analysis. The tool and technique you are using is a simulation where the project mode is computed many time with the input values chosen at random for each iteration. The goal is to create a probability distribution from the iterations for the project schedule. What technique will you use with this simulation?
Analogous modeling.
Monte Carlo Technique.
Expected Monetary Value.
Pareto modeling.

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which project reserves should the project manager use to budget for known risks?
Sponsor reserve.
Contingency reserve.
Budget reserve.
Management reserve.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The project manager for project A was expecting the mobilization of critical equipment from another project, project B. However, a day before the mobilization was scheduled, another project manager notifies project A's project manager that the equipment would not be available for at least another month due to delayed activities for project B. This has jeopardized meeting a critical milestone for project A. How should project A's project manager avoid this situation in the future?
Request that the other project manager inform if any additional delays are expected.
Ask the other project manager to officially confirm the new date in writing.
Request that the other project manager be added to relevant reports.
Prepare a contingency response plan to implement when delays occur.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What type of reserve should be allocated for the risks that are identified but unclear. How can this risk be proactively managed?
Cost budget.
Management.
Budget.
Contingency.

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A project management team has identified a large number of risks during its risk identification sessions. It was noticed that it would not have the time and resources to quantitatively analyze all of them. The team also agreed that not all of these risks would justify the effort necessary to dig deeply into them. What should the team do next?
Perform qualitative risk analysis to prioritize the risks.
Perform quantitative risk analysis to numerically analyze risks.
Implement agreed upon risk response plans.
Plan risk responses for each of the identified risks.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?