PMI SH - Address and Remove Impediments, Obstacles, and Blockers

PMI SH - Address and Remove Impediments, Obstacles, and Blockers

1st - 3rd Grade

28 Qs

quiz-placeholder

Similar activities

Leadership and teamwork

Leadership and teamwork

1st - 3rd Grade

25 Qs

open assessment 3

open assessment 3

1st Grade

30 Qs

Project Management Part 1

Project Management Part 1

1st Grade

30 Qs

Project Management Opportunity Quiz

Project Management Opportunity Quiz

1st Grade

23 Qs

RMP - 4. RISK ANALYSIS

RMP - 4. RISK ANALYSIS

1st Grade

23 Qs

RMP - 3. RISK IDENTIFICATION

RMP - 3. RISK IDENTIFICATION

1st Grade

24 Qs

PMI SH - Empower Team Members and Stakeholders

PMI SH - Empower Team Members and Stakeholders

1st - 3rd Grade

29 Qs

PMI SH - Build and Lead a Team (0.5)

PMI SH - Build and Lead a Team (0.5)

1st Grade

30 Qs

PMI SH - Address and Remove Impediments, Obstacles, and Blockers

PMI SH - Address and Remove Impediments, Obstacles, and Blockers

Assessment

Quiz

Professional Development

1st - 3rd Grade

Hard

Created by

sudiyuwono wowo

FREE Resource

28 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project integrates with several systems developed by various vendors and one of these vendors has gone out of business. What should the project manager do first?

Meet with this vendor to identify a replacement.

Review the risk register and update the issue log.

Calculate the delay and notify the project sponsor of the new timeline.

Negotiate with another vendor to produce the deliverable.

Answer explanation

Solution: B. Review the risk register and update the issue log.

The risk register contains response strategies in situations like these. The project manager should review the risk register for potential action plans, and update the issue log with the issue of the absent vendor. The issue log is fundamentally about corrective actions since the project has deviated from the plan.

The other answer choices are incorrect. Calculating the delay, meeting the vendor for a replacement, and negotiating with another vendor for deliverable are the next steps after risk register and updated and risk components are performed

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager working on an agile project discovers that the allocated budget and resources are insufficient to cover the estimated total cost. The PMO recommended the development of requirements prioritization model.

What should the project manager take into consideration in the model?

Cost, associated risk, and company culture.

Associated risk and company culture.

Cost and associated risk.

Associated cost impediments.

Answer explanation

Solution: C. Cost and associated risk

For each feature, the project manager should identify the benefits of implementing it and the impact of skipping it, in addition to the cost and associated risk.

The other answer choices are incorrect. Company culture has the same impact on all the projects and requirements, therefore it can't be used to prioritize requirements. Cost impediments are not yet known, therefore risk should be a prioritization criterion.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

As part of a temporary assignment, a project manager is leading a business project. During a daily status meeting, it was discovered that the development team had not completed a critical task. This issue is delaying the current iteration. The ability to take the actions needed to address this issue is beyond the authority of the project team.

What should the project manager do?

Delay the current iteration and inform the stakeholders of the issue.

Invite the project team to a swarming session to define a solution.

Adjust the project timeline to accommodate the development delay.

Escalate the issue to the project sponsor to define the next steps.

Answer explanation

Solution: D. Escalate the issue to the project sponsor to define the next steps.

For decisions that are beyond the authority of the project team to decide, the project team can investigate alternatives and escalate the decision to the project sponsor. The project sponsor provides decision leadership that is outside of the authority and position power of the project manager and project team.

The other options may not be appropriate or effective if the project manager does not have the authority to take the necessary actions.

Delaying the current iteration, hosting a swarming session, or adjusting the project timeline may not be feasible and do not address the issue of authority or decision-making. 

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An organization decides to implement the Scrum delivery framework. The project manager is using an impediment board with the Scrum team to identify and raise impediments.

What should happen after the impediments are recorded?

Address the highest priority impediments from the log and ensure that it is removed so that the team can continue to reach the sprint’s objective.

Prioritize impediments based on their levels of importance and in relation to those that are already on the log.

Publish and post the impediments log and make it visible to everyone.

Communicate that the impediment is removed to the involved parties and update the impediments log.

Answer explanation

Solution: B. Prioritize impediments based on their levels of importance and in relation to those that are already on the log

The process used to create, monitor, and maintain the impediments log begins with the daily standup meeting. It is the best time to record impediments in the impediments log as each team member reveals them. Then, the impediments should be prioritized based on their levels of importance and in relation to those on that are already on the log.

The other answer choices are incorrect because they come after the impediments have been prioritized.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


Question

A project team's performance has declined for the last three iterations. Some of the team members are disappointed, and raise their concerns during the retrospective meeting.

What should the project manager do?

Identify potential failure points based on the iteration workload.

Motivate the team to perform better.

Focus on remediation, not merely on correcting symptoms.

Compare the team's performance against other project teams.

Answer explanation

Solution: C. Focus on remediation, not merely on correcting symptoms.

Root cause analysis.

Root cause analysis is designed to identify and correct the fundamental cause of a problem. It helps focus remediation not on merely correcting symptoms but on preventing the recurrence of problems. This type of analysis is especially useful as a method to proactively forecast probable events before they occur.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on the development of a business case to secure funding and resources. What is needed to ensure that the right priority is assigned to the project?

Developing the most efficient delivery plan

Developing a clear and detailed project schedule

Aligning the project with company’s goals and objectives

Aligning the project with company’s roadmap

Answer explanation

Solution: C. Aligning the project with company’s goals and objectives

To ensure that the right priority is assigned to the project, it is crucial to align it with the company's goals and objectives. This ensures that the project is directly contributing to the strategic direction and priorities of the organization. By aligning the project with the company's goals, decision-makers can assess its relevance, strategic importance, and potential impact, which can help in securing funding and resources.

The other answer choices are incorrect as they focus more on the efficiency and scheduling aspects of project delivery, which are important considerations but may not directly address assigning the right priority to the project. Aligning with company goals and objectives is a broader and more fundamental consideration for assigning project priority than the roadmap.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A goal has been set at four months for a project team to distribute a product. Unfortunately, it will be difficult to adhere to that time frame due to team members having individual tasks to complete.

How should the project manager handle this situation?

Encourage members of the team to alter their tasks in order to not impede with meeting the project deadline.

Aid team members in prioritizing their personal tasks against the project's goals.

Postpone the delivery date of the project to a later time so the team can complete their personal tasks.

Request a delay to the teams’ individual tasks and offer assistance finding alternative times to complete tasks outside of work hours.

Answer explanation

Solution: B. Aid team members in prioritizing their personal tasks against the project's goals

In the case that there is limited time, the team must prioritize the delivery-related tasks to get the product distributed on time. The project manager should handle this situation by aiding team members in prioritizing their personal tasks against the project's goals.

The other answer choices do not lead to the desired outcome.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?