1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Activity-based costing:

Uses a plant-wide overhead rate to assign overhead

Is not expensive to implement

Typically applies overhead costs using direct labor-hours

Uses multiple activity rates

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is not correct about ABC:

Less accurate

Difficult to implement

Time consuming

Massive amount of data

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The first step of ABC is the analysis and identification of the company’s activities

TRUE

FALSE

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

ABC Formula =

Cost pool in Total/Cost Driver

Cost pool in Total + Cost Driver

Cost pool in Total - Cost Driver

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Under ABC an event that causes the consumption of overhead resources in an organization called

Activity Cost pooling

Activity

Overhead

Allocation

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is not a correct of advantages ABC method ?

Accurate cost computation

Allows an in-depth product analysis

More economical

Costly

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is not a correct of Disadvantages ABC method ?

Costly

Time – consuming and more complex:

Accurate cost computation

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?