
2023S Review Questions 1
Authored by Lcit Pmguild
Business
Professional Development
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A customer wants to add new features to the project deliverable. Before the project manager can begin work on these new features, what should the project manager do first?
A customer wants to add new features to the project deliverable. Before the project manager can begin work on these new features, what should the project manager do first?
Draft the change request in the appropriate format to seek approval from the change control board (CCB) and start working on the new features only after approval is given
Notify the project sponsor and wait for their approval to work on these new features
Consult a subject matter expert (SME) and start working on the new features after there are no further concerns raised
Answer explanation
The Change control board is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project and for recording and communicating such decisions. The options to email the project manager, notify project sponsor and consult a SME are not sufficient change control actions to be completed before spending resources on the new feature.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a status review meeting, it was determined that the product will not meet project scope requirements in a particular scenario. What should the project manager do?
Perform risk analysis and update project scope.
Initiate integrated change control process.
Review the baselines to determine the critical path.
Inform customer and negotiate an extended deadline.
Answer explanation
The product not meeting project scope is a "Risk" that needs to be managed. This is managed through Integrated Change Control Process. Project scope may change to include this particular scenario after the CCP is initiated. There is no baseline review nor renegotiation with the customer until after the CCP is initiated.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
After all deliverables have been completed, a project manager needs to formally close a project. What should the project manager do?
Update the project documents with quality control measurements to prove deliverables have been met.
Obtain stakeholder acceptance and initiate project closeout.
Release the project team and estimate any unused funds.
Incorporate the issue log into the lessons learned register to produce the final report.
Answer explanation
The PM should obtain the acceptance of the Stakeholders who had initiated the project. The remaining answers are activities to be completed as part of the Project Closeout and are, therefore, not the correct answer.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is assigned to a project that has completed the planning phase. The project sponsor is confident that the project management plan has allowed for sufficient budget and scheduled time. The project manager believes that unforeseen events could affect the ability to complete the project successfully. What should the project manager do?
Identify and evaluate potential risks and develop a risk action plan.
Meet with the project sponsor to request additional funding to mitigate potential risks.
Discuss the risk potential with the functional manager and identify resources that could ensure project success.
Document potential constraints and limitations in the risk management plan.
Answer explanation
The correct response is to identify and evaluate risks, and develop an action plan. The project manager needs to be proactive and anticipate uncertain events and create plans to avoid, mitigate, transfer, or accept them. Requesting additional funding is premature until the risks are understood, as are other resource discussions with the functional manager. The risk management plan describes the process by which the project approaches risk, and nothing in the question indicates that it is inadequate; documenting constraints and limitations also is premature.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During the integration phase of a complex system improvement project, an upgrade to one component causes an outage on an existing critical component that is currently in use by all departments to access inventory data. What should the project manager do first?
Consult the operations plan to determine the best way to resolve the issue.
Follow the communications management plan to notify the stakeholders of the issue.
Update the issue log with details about a final solution.
Review the strategy documented in the risk management plan to manage the issue.
Answer explanation
Because a project issue has caused an unexpected impact to stakeholders, they must be notified, per the communications management plan. Resolving the issue and updating the issue log will be done afterwards, but the communication must come first. A strategy or contingency to respond to the issue would be documented in the risk register, which is not part of the risk management plan.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager and the project team identified risks, performed a qualitative risk analysis, and prepared a risk response plan. However, delays in the response to risk events are affecting the project schedule. How would assigning risk owners to the risk responses help avoid these delays?
Risk owners work with the project sponsor to ensure the risk response plan will be effective.
Risk owners identify likely constraints and assumptions before the risk events occur.
Risk owners are responsible for implementing the appropriate risk response strategy.
The risk report assigns management of delays in the project schedule to the appropriate risk owner.
Answer explanation
Risk owners for each risk are nominated as part of the Identify Risks process and confirmed during the Perform Qualitative Risk Analysis process. Risk owners take responsibility for planning the risk response and ensuring that it is implemented. If a Risk Owner is not assigned to a risk then the risk response will not be implemented in a timely manner and delays to the schedule could occur. Working to ensure the response plan addressed the risk and identifying constraints and assumptions does not address the situation of the delay in schedule. The risk report provides information on sources of overall project risk and responses. It does not specify schedule delays.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
While reviewing the approved project schedule, the project manager realizes that the milestones are unrealistic due to longer-than-expected procurement lead times for certain key project components. The project manager needs to update the schedule baseline to reflect the long lead times. What should the project manager do first?
Modify the work breakdown structure (WBS).
Update the assumption log.
Modify the procurement management plan.
Submit a change request.
Answer explanation
Change request is the correct answer as every baseline change should go through an integrated change control process. Procurement lead times are the issue here. Therefore, there is no need to modify the WBS nor to update the assumption log. It is the lead times that were defined but not accounted in schedule baseline. There is no need to change the procurement management plan.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?