SCOPE CAPM QUIZ

SCOPE CAPM QUIZ

Professional Development

10 Qs

quiz-placeholder

Similar activities

Projects and Programs Management #3

Projects and Programs Management #3

University - Professional Development

10 Qs

Pre Test Ms. Project

Pre Test Ms. Project

Professional Development

10 Qs

Project Management - Quiz 1

Project Management - Quiz 1

Professional Development

10 Qs

Scrum Artifacts - Homework

Scrum Artifacts - Homework

Professional Development

10 Qs

ISO 9001:2015

ISO 9001:2015

Professional Development

10 Qs

Construction Cost Estimating and Analysis Quiz No. 1

Construction Cost Estimating and Analysis Quiz No. 1

Professional Development

10 Qs

How well do you know R.A. 9184 and its IRR?

How well do you know R.A. 9184 and its IRR?

Professional Development

10 Qs

Requirement

Requirement

Professional Development

14 Qs

SCOPE CAPM QUIZ

SCOPE CAPM QUIZ

Assessment

Quiz

Other

Professional Development

Easy

Created by

Pedro Pablo Rosa

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

1 min • 1 pt

You are a project manager. You’re heading up a small project to promote a new line of product to be sold  You know that the purpose of the project scope management plan and requirements management plan provide

which of the following? (Choose three.)

A. They help set a clear vision and mission for the project.

B. They are used to further elaborate the project charter, which contains a list of high-level requirements needed to satisfy stakeholder expectations before starting the project management plan.

C. They serve as an agreement between the project management team and the project customer to document and agree on the work of the project and what it will produce.

D. They are both used to plan and manage the scope of the project

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following statements is true about the work breakdown structure (WBS)?

A. The WBS is a simple list of project activities in chart form.

B. The WBS is a hierarchical decomposition of the total scope of work

C. The WBS is the same as the organizational breakdown structure (OBS)

D. The WBS is the bill of materials (BOM) needed to accomplish the project objectives

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Agile scope planning is especially useful when

A. Solution requirements area emerging all the time

B. Quality requirements are not stable

C. Business requirements are not stable

D. Scope is well understood at beginning

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

On a agile software development project, the project manager asks business stakeholders to create user stories. The main purpose of a user story is:

A. To perform what-if analysis

B. To communicate progress

C. To create a record of issues encountered on the project

D. To document features or functions required by stakeholders

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Uncontrolled project scope changes are often referred to as

A. Scope verification

B. Scope control

C. value Added Scope

D. Scope creep

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The following is an example of a constraint associated with the project scope that limits the team's options in scope definition

A. The threat of a strike by a subcontractor.

B. Existing relationships with sellers, suppliers, or others in the supply chain

C. A predefined budget or any imposed dates or schedule milestones

D. The method used to measure project performance.

7.

MULTIPLE SELECT QUESTION

1 min • 1 pt

You are a project manager working on a large, complex project. You’ve constructed the WBS for this project, and all of the work package levels are subprojects of this project. You’ve requested that the subproject managers report to you in three weeks with their individual WBSs constructed. Which of the following statements are correct? (Choose three.)

A. The work package level is decomposed to create the activity list.

B. The work package level is the lowest level in the WBS and is known as a user story on an agile project.

C. The work package level facilitates resource assignments.

D. The work package level facilitates cost and time estimates.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?