UKHO Improvement Technicians Data Rev 04

UKHO Improvement Technicians Data Rev 04

1st Grade

10 Qs

quiz-placeholder

Similar activities

2022 Winter Olympics

2022 Winter Olympics

1st - 5th Grade

10 Qs

Evaluating students' learning

Evaluating students' learning

1st - 3rd Grade

12 Qs

Impact quiz

Impact quiz

1st - 3rd Grade

11 Qs

ESP Knowledge

ESP Knowledge

1st Grade

6 Qs

My Project Quiz!

My Project Quiz!

KG - University

7 Qs

Home ownership terminology

Home ownership terminology

1st - 3rd Grade

8 Qs

AFMP Day 6

AFMP Day 6

1st - 3rd Grade

10 Qs

Design Thinking Vocab

Design Thinking Vocab

1st - 5th Grade

14 Qs

UKHO Improvement Technicians Data Rev 04

UKHO Improvement Technicians Data Rev 04

Assessment

Quiz

Education

1st Grade

Easy

Created by

Gary Carr

Used 6+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which Authorization Document allows the Project Manager to allocate project resources?

The S.O.W

The W.B.S

The Project Charter

The assumptions Log

2.

DRAG AND DROP QUESTION

1 min • 1 pt

The ​ (a)    analysis is a project management process that evaluates different scenarios to predict their ​ (b)   – both positive and ​ (c)   – on the project ​ (d)  

what-if scenario
effects
negative
objectives

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which Formula represents the Beta or PERT distribution used for Estimating in Projects?

tE = (tO+tM+tP) / 3

tE = (tO+4tM+tP) / 6

4.

DRAG AND DROP QUESTION

1 min • 1 pt

The ​ (a)   of Six Sigma is to achieve a level of ​ (b)   that is nearly perfect, with only 3.4 ​ (c)   per ​ (d)   ​ (e)   .

goal
quality
defects
million
opportunities

5.

DRAG AND DROP QUESTION

1 min • 1 pt

​ (a)   concerns itself, in ​ (b)   eyes, as being about ​ (c)   through ​ (d)   reduction; through a focus on the mechanics of the ​ (e)   itself.

PDCA
Deming’s
process improvement
defect
process

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

EVM is an excellent tool to use in order to manage and control the project as it quickly shows any variances from the project baselines (Time & Cost).

True

False

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An Iteration Burn Down Chart shows?

Actual Work Remaining

Ideal Work Remaining

Forecast of Work Remaining

All options listed

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?