Agile Exam Preparation

Agile Exam Preparation

1st Grade

10 Qs

quiz-placeholder

Similar activities

learning about glady's

learning about glady's

KG - Professional Development

12 Qs

17 Days of SDGs Quiz - Day 10 (English)

17 Days of SDGs Quiz - Day 10 (English)

KG - Professional Development

15 Qs

Compubotics Siri 2

Compubotics Siri 2

1st - 3rd Grade

10 Qs

Post Test Hoki/DMS - Job Title Admin Head

Post Test Hoki/DMS - Job Title Admin Head

1st - 2nd Grade

15 Qs

CINTURON BLANCO AMARILLO

CINTURON BLANCO AMARILLO

1st - 9th Grade

11 Qs

Safe Physical Training through Covid 19

Safe Physical Training through Covid 19

1st - 12th Grade

10 Qs

MARKI POJAZDÓW

MARKI POJAZDÓW

1st - 3rd Grade

11 Qs

Large numbers, decimals, percentages and fractions

Large numbers, decimals, percentages and fractions

1st Grade

15 Qs

Agile Exam Preparation

Agile Exam Preparation

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

sudiyuwono wowo

Used 8+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A newly formed agile project team has developers that work on front-end, back-end, testing, and requirements development. Only one developer has the specific knowledge and skills key to several project iterations.

How should the team minimize the risk of temporarily losing this developer?

Add specialty people to the team to alleviate potential bottlenecks and increase performance.

Create a working agreement to minimize the out-of-office time that any member may use during the project.

Rotate team members on and off the team as needs rise and fall.

Begin pair programming to increase team members' experience.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Agile team members are gathering inputs for planning their first iteration of software development project. Which of the following would help the team the most to save time and reduce a risk of a failure?

Velocity values from similar project executed by another team

Retrospective decision from the best team in the organization

The source code of similar product from previous project

Definition of Done of the similar product from previous project

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Scrum Master is conducting sprint retrospective meeting which is becoming contentious. Which of the following action might the Scrum master take to address team conflict?

Intervening at the first sign of conflict to avoid escalation and potentially damaged relationship

Intervening when heated discussion occur, and taking a break if needed to address individuals privately.

Addressing inappropriate behavior during the meeting to hold individual accountable to the team

Using authority as Scrum master to decide for the team when the discussion reachs an impasse

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After completing three iterations, an Agile team has determine that it will take 292 story point to complete the remaining portion of the Project. The average velocity of the Team for the first three iterations was 30 story points. How many additional iterations will it take for the team to complete the Project?

11 iterations

8 iterations

9 iterations

10 iterations

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When Agile team focus on creating comprehensive documentation, they will have less time to :

Play collaborative games to have fun at work

Prepare progress status reports for Management

Response to changes requested by the Customer

Negotiate contract with the third-party vendors.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile team has been working overtime for the last few iterations. The project manager has decided that from now on the team should maintain a 40-hour workweek. What is the most likely reason behind the project manager's decision?

To minimize the amount of work in progress

To prioritize high-risk user stories for the next sprint

To deliver working software frequently

To promote sustainable development

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A few days before the end of the last iteration, the team informs the project manager that they will be unable to finish two work packages, A and B, because the WBS is insufficiently refined. The team thinks they might be able to complete package A on time but will need an additional week to complete package B which has a higher priority. What is the best course of action for the project manager?

Instruct the team to complete package B since it has a higher priority

Extend the iteration length in order to finish both packages A and B

Facilitate to Crashing & Fast tracking

Consult with the product owner and make a decision accordingly

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?