1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The five Project Management Process Groups are:

Planning, Checking, Directing, Monitoring, and Recording.

Initiating, Planning, Executing, Monitoring and Controlling, and Closing.

Planning, Executing, Directing, Closing, and Commissioning.

Initiating, Executing, Monitoring, Evaluating, and Closing

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which process uses up most of the budget in a project?

Integrating

Planning

Executing

Monitoring and Controlling

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A change control board is

A formally constituted group of stakeholders responsible for minimizing the number of approved changes, with all decisions and recommendations being recorded.

A formally constituted group of stakeholders responsible for reviewing, evaluating, approving, delaying or rejecting changes to the project, with all decisions and recommendations being recorded.

Functionally equivalent to a project steering committee.

Any group of stakeholders that meets to review or approve changes

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The sequence of activities that cannot be delayed during the course of the project is referred to as the:

Critical path

Master schedule

Slack line

Action plan

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your project budget is USD 400,000. Most of this money will be spent during:

Project plan development.

Project plan execution.

Project control.

Project initiation.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your team is in the middle of executing a project that is now projected to run three weeks too long. Which of the following adjustments would allow the project to be delivered on time?

Substitute a lesser experienced programmer for a more experienced one

Move resources from a non-critical task to a critical path task

Modify the purchase of new equipment to less expensive equipment

Allow a tester on the project to temporarily work on another, more critical project

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

One of the following groups is NOT a process group – but which one?

Planning

Integrating

Closing

Executing

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

Already have an account?