
Session 2 PMIS Exit
Authored by Jean Ukwizabigira
Other
University
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a meeting, a project manager learns that a business result needs to be delivered in four weeks, although the original plan was sixteen weeks. The project manager also hears that there is no available technical resource who might be able to join the team. The project manager knows the technical resource manager because they worked together on a previous project.
What is the first thing the project manager should do?
Notify the project sponsor about the lack of a technical resource.
Immediately escalate the issue to decision makers in the organization
Check with the technical resource manager to see if there is an available technical resource.
Since time is short, hire an outside party to meet the need for a technical resource
Answer explanation
A Per Agile manifesto, it values individual and interactions over processes and tools. Thus, it is best to meet with the resource manager to understand the real situation rather than informing sponsor first which might be the false alarm.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A customer is not satisfied with the delivered product, saying that it was not what they expected. The project manager is surprised, because the agile development team delivered the product several iterations early.
What is one way that the project manager could have avoided this result?
Required team sign off for each of the constant changes to the requirements
Set aside more resources for product testing after changes are made
Made sure that the customer was aware of the value of demos
Ensured that the team fully participated in developing the project scope
Answer explanation
C The customer was not engaged enough in the project. The iteration review is the best mechanism for the team to demonstrate working software and for the customer to give feedback to ensure that their expectations are met.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
After six iterations, significant variations have occurred to project scope and schedule. These are due to the customer's technology regulations and security policies, which are regularly reviewed. The project manager wants to suggest a new approach to the next iteration to avoid possible delays.
What should the project manager do first?
Rank the importance of each improvement item, then implement actions identified during the last retrospective.
Engage in a cost-benefit analysis that can help predict the profits that could be realized through the use of new technology for the next phase.
Research new technology trends and management tools that have been successful on similar projects.
Use a backlog refinement meeting and include the customer's change requests in the discussion.
Answer explanation
A The retrospective is used to review lessons learned and suggest corrective actions for the next iterations.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During one daily standup meeting, team members indicate that they are having to engage in rework because there seems to be too much up-front work.
How should the project manager respond to this concern?
Try using a Kanban board for reviews.
Request that team members explicitly implement time boxing
Request that the project owner maximizes the product value
Engage in a process to manage a reduction in the product backlog.
Answer explanation
B Shorter iterations allow for managing functionalities more closely should the team keep working on a minimum Viable Product.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager receives the following for a new project:
-assumptions
-restrictions
-preliminary scope
After receiving this information, what should the project manager do first?
Review and understand the business case and project goals.
. Put together the project team and assign project tasks.
Build the project schedule and determine the critical path.
Ensure project charter approval is obtained from the sponsor.
Answer explanation
A
The business case and project goals need to be understood first before a charter can be written. Building a team and a schedule come later in the process
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Sustainable Agriculture
Quiz
•
University
9 questions
St.Francis of Assisi
Quiz
•
5th Grade - University
10 questions
BUILDING CONSTRUCTION CONTRACTS TYPE
Quiz
•
University
10 questions
Clare and Barry's TV Soap Quiz
Quiz
•
KG - Professional Dev...
10 questions
Chapter 11: OHP review
Quiz
•
University
9 questions
star wars
Quiz
•
3rd Grade - Professio...
10 questions
RAPAT TELECONFERENCE
Quiz
•
12th Grade - University
10 questions
Memory
Quiz
•
University
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade
Discover more resources for Other
12 questions
IREAD Week 4 - Review
Quiz
•
3rd Grade - University
23 questions
Subject Verb Agreement
Quiz
•
9th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University
5 questions
Poetry Interpretation
Interactive video
•
4th Grade - University
19 questions
Black History Month Trivia
Quiz
•
6th Grade - Professio...
15 questions
Review1
Quiz
•
University
15 questions
Pre1
Quiz
•
University