1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The ability of stakeholders to influence the project is typically highest at which stage?

initiating

planning

closing

executing

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of organizational structure utilizes full-time project support staff?

composite

functional

matrix

projected

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Prom, senior picnic, and graduation are examples of:

operations

PMBOK

programs

projects

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Renovating a kitchen, planning a vacation, and starting a school club are all examples of:

operations

programs

projects

communications

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Joe holds a team meeting to discuss lessons learned. He is in which process stage?

closing

planning

executing

monitoring/

controlling

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

the organizational structure in which the project manager has the greatest amount of authority is a:

composite

functional

projectized

matrix

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Paul is contacting a list of potential suppliers to request price quotes for a key project material. He is in which process stage?

initiating

executing

monitoring/

controlling

closing

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?