1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is used to figure long distances that need to be paved along the highway?
Estimating tonnage
Surveying
Stationing
Distance calculations
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
If you began paving at station 1850+25.00 and by 3:00 you were at station 2160+50.00, how many feet were paved?
30,250'
31,025'
32,500'
33,010'
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is 1/2 of the total distance across the center of a circle?
pi
Diameter
Radius
Circumference
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If you began paving from station 2854+30.00 to station 3265+78.00, how many feet were paved?
41,148
41,543
41,854
42,018
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the square yardage of the area?
9,450 sq. ft.
7,725 sq. ft.
6,750 sq. ft.
8,750 sq. ft.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If you need to order 700 tons of asphalt for a job and want to have 10% extra, how many tons should you order?
770 tons
760 tons
750 tons
780 tons
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
If the application rate for your job was 0.09 gallons per square yard and you had 45,025 square yards to cover, how many gallons of tack are needed?
4,550.75
4,250.50
4,052.25
4,425.75
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?