CAPM Quiz -  Domain I

CAPM Quiz - Domain I

Professional Development

50 Qs

quiz-placeholder

Similar activities

BUSINESS ENGLISH COLLOCATIONS ( DO - MAKE - TAKE)

BUSINESS ENGLISH COLLOCATIONS ( DO - MAKE - TAKE)

Professional Development

46 Qs

Sharepoint Administration Revision

Sharepoint Administration Revision

Professional Development

48 Qs

PMP 380 mock questions - Chapter 2 (Process)

PMP 380 mock questions - Chapter 2 (Process)

Professional Development

50 Qs

CompTIA Project+ Practice Tests, Chapter #4 questions #106-158

CompTIA Project+ Practice Tests, Chapter #4 questions #106-158

Professional Development

53 Qs

PMP Exam Prep 2024 - Bonus Q&A - Chapter 7 - Project Comm Mngmt

PMP Exam Prep 2024 - Bonus Q&A - Chapter 7 - Project Comm Mngmt

Professional Development

50 Qs

Project Management Fundamental : Post-test

Project Management Fundamental : Post-test

Professional Development

50 Qs

SIMPLE PAST X PRESENT PERFECT

SIMPLE PAST X PRESENT PERFECT

Professional Development

50 Qs

PMI ACP SG NOKIA Agile Extra 45 Qns

PMI ACP SG NOKIA Agile Extra 45 Qns

Professional Development

45 Qs

CAPM Quiz -  Domain I

CAPM Quiz - Domain I

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Training eNetwoQ ServIT Indonesia

Used 2+ times

FREE Resource

50 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A temporary endeavor with a defined beginning and end, undertaken to create a unique product, service, or result. What the definition for it?
Program
Project
Portfolio
Operation

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

When the interface between project and operation will happen as the transfer knowledge before run the product or service?
Planning Process
Execution Process
Monitoring Process
Closing Process

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project team that is experienced in the waterfall project management approach has been assigned to their first agile project. To make the transition easier, it has been decided to keep some waterfall approach elements in place. What the Project approach appropriate to use?
Agile because high value and fast adapt
Predictive with some documents as basis of planning
Hybrid because the transition condition
Fallback to a waterfall project management framework going forward

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

CSRO Project has been decided by Sponsor. After the Processiong of Project Charter, You are selected as Project Manager. What should you to start your job?
Define Risk on Risk Register
Define Assumption on Assumption Log
Update Communication Management Plan
Update Stakeholder List

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Where we should update the Constraint of the Project while in Initiation and Planning Phase?
Risk Register
Change Request
Assumption Log
Lesson Learned

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

What are the Project Management Code of ethics, which one of least likely?
Responsibility and Respect
Fairness and honesty
Responsibility and honesty
Listening and honesty

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Organization want to increase their value from current state to future state thru the projects. What should organization do to define which projects that will be taken on that?
Conduct need assessment
Review the Risk and Stakeholder
Review the Project Charter
Update the OPA to improve better process on Future

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?