5. Project Scheduling

5. Project Scheduling

University

10 Qs

quiz-placeholder

Similar activities

PAD101.QUIZ03.Planning

PAD101.QUIZ03.Planning

University - Professional Development

15 Qs

Time management_Survey

Time management_Survey

University

10 Qs

Life and Career Skills

Life and Career Skills

University

10 Qs

Project Costing

Project Costing

University

10 Qs

Homeroom Activity

Homeroom Activity

8th Grade - University

15 Qs

G 6_SS_CH 13 - The Value of Work

G 6_SS_CH 13 - The Value of Work

6th Grade - University

10 Qs

Philosophical Perspectives About the Self

Philosophical Perspectives About the Self

University

15 Qs

Quiz 1

Quiz 1

University

10 Qs

5. Project Scheduling

5. Project Scheduling

Assessment

Quiz

Social Studies

University

Hard

Created by

Akvilė Rykovė

Used 9+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The first step in the development of a schedule is a:

Listing of the activities

Determination of dependencies

Calculation of effort

Calculation of durations

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following generally cannot be validated using a work breakdown structure?

Schedule control

Cost control

Quality control

Risk management

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Optimistic, pessimistic, and most likely activity times are associated with:

PERT

GERT

PDM

ADM

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is (are) the benefit(s) of developing a WBS to low levels?

Better estimation of costs

Better control

Less likely that something will “fall through the cracks”

All other answers are correct

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The major disadvantage of using bar charts to manage a project is that bar charts:

Do not show dependencies between activities

Are ineffective for projects under one year in length

Are ineffective for projects under $1 million in size

Do not identify start and end dates of a schedule

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The most common “constraint” or relationship in a precedence network is:

Start-to-start

Start-to-finish

Finish-to-start

Finish-to-finish

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The work breakdown structure “control points” for the management of a project are the:

Milestones

Work packages

Activities

Constraints

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?