1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The first step in the development of a schedule is a:
Listing of the activities
Determination of dependencies
Calculation of effort
Calculation of durations
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following generally cannot be validated using a work breakdown structure?
Schedule control
Cost control
Quality control
Risk management
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Optimistic, pessimistic, and most likely activity times are associated with:
PERT
GERT
PDM
ADM
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is (are) the benefit(s) of developing a WBS to low levels?
Better estimation of costs
Better control
Less likely that something will “fall through the cracks”
All other answers are correct
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The major disadvantage of using bar charts to manage a project is that bar charts:
Do not show dependencies between activities
Are ineffective for projects under one year in length
Are ineffective for projects under $1 million in size
Do not identify start and end dates of a schedule
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The most common “constraint” or relationship in a precedence network is:
Start-to-start
Start-to-finish
Finish-to-start
Finish-to-finish
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The work breakdown structure “control points” for the management of a project are the:
Milestones
Work packages
Activities
Constraints
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?