5. Project Scheduling

5. Project Scheduling

University

10 Qs

quiz-placeholder

Similar activities

PRINCIPLES OF MANAGEMENT DPB10023

PRINCIPLES OF MANAGEMENT DPB10023

University

14 Qs

Time Management

Time Management

University

12 Qs

Time management_Survey

Time management_Survey

University

10 Qs

Life and Career Skills

Life and Career Skills

University

10 Qs

General Purpose and the Vertical Logic of the LogFrame

General Purpose and the Vertical Logic of the LogFrame

University

9 Qs

Homeroom Activity

Homeroom Activity

8th Grade - University

15 Qs

The Boy Who Harnessed the Wind

The Boy Who Harnessed the Wind

6th Grade - University

15 Qs

BMC (week 3)

BMC (week 3)

University

12 Qs

5. Project Scheduling

5. Project Scheduling

Assessment

Quiz

Social Studies

University

Hard

Created by

Akvilė Rykovė

Used 9+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The first step in the development of a schedule is a:

Listing of the activities

Determination of dependencies

Calculation of effort

Calculation of durations

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following generally cannot be validated using a work breakdown structure?

Schedule control

Cost control

Quality control

Risk management

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Optimistic, pessimistic, and most likely activity times are associated with:

PERT

GERT

PDM

ADM

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is (are) the benefit(s) of developing a WBS to low levels?

Better estimation of costs

Better control

Less likely that something will “fall through the cracks”

All other answers are correct

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The major disadvantage of using bar charts to manage a project is that bar charts:

Do not show dependencies between activities

Are ineffective for projects under one year in length

Are ineffective for projects under $1 million in size

Do not identify start and end dates of a schedule

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The most common “constraint” or relationship in a precedence network is:

Start-to-start

Start-to-finish

Finish-to-start

Finish-to-finish

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The work breakdown structure “control points” for the management of a project are the:

Milestones

Work packages

Activities

Constraints

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?