A project manager is managing an industrial project. He needs a batch of 1000 custom-made, identical filters for the project. Due to their high importance, the project manager chooses a reliable and well-known supplier to produce these filters. Knowing that a tested filter should be thrown away since it couldn't be reutilized, what should the project manager do?
PMP 380 mock questions - Full mock - part 2

Quiz
•
Professional Development
•
Professional Development
•
Medium

Patrick Pepin
Used 3+ times
FREE Resource
60 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Skip inspection, since he trusts that the supplier will deliver the filter according to a specifications
Order more than 1000 filters to perform acceptance sampling on the batch surplus
Require the seller to provide a performance certificate of the filters Raw materials
Conduct a 100% inspection upon delivery, then order another batch of 1000 filters if he satisfied with the quality
Answer explanation
when conducting a 100% inspection is not possible, the project manager should opt for the sampling of a certain number from a batch (also known as a lot) of the items and perform an inspection of the sample. Since tested filters cannot be used for the project, the best course of action is to order more than the required items in order to perform the acceptance sampling.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During project execution, the project manager found out that tasks were not being performed in the right order at the right time which resulted in rework and bad morale among the project team.
Which project management tool, the project manager implemented deal with this type of issue?
Organization chart
RACI Matrix
Communications management plan
Work authorization system
Answer explanation
A Work authorization system Is a set of formal documented procedures that establishes our project work will be authorized to ensure that work is done at the right time, and in the correct sequence.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has taken over the management of a climate-smart agriculture project, replacing the project manager who has quit. At the Beginning of the execution phase, the project manager notices that team members have different opinions concerning the project, work and deliverables, as well as the overall complexity level. What should the project manager do?
They should not intervene. Instead, they should allow the team enough time to get familiar with the project scope.
They should identify and assess potential risks caused by this divergence of opinion, then develop the plant to manage and respond to these risks
They should organize a meeting involving all team members to identify and resolve, misunderstandings in order to avoid issues, disintegration, and rework
They should talk to each team member separately to explain the project requirements
Answer explanation
The best course of action in this case is to use problem-solving or collaboration techniques to resolve this issue. Therefore, in order to avoid any future problems, disintegration, or rework, organizing meetings is the best option to identify and resolve, misunderstandings a multi members. The withdrawal technique should not be used in critical conflicts, related to project work, and deliverables, like in this scenario. Planning risks is supposed to take place in the planning phase. But, since the project there's in the execution phase, the project manager needs to follow the establish plan and resolve any occurring risks, pre-identified or not. Change request and be issued to manage an impactful risk. The best communication method is interactive, face-to-face communication, that's why talking to each team member individually as effective as gathering all team members in one meeting so they can interact with each other.
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
A project manager at Max data has just put the finishing touches on her final project report before meeting with her manager. She spent the last few weeks holding numerous lessons learns sessions to get feedback from project participants for the final report. For what reasons did the project manager hold lessons learned sessions? (Select three)
lessons learned databases are an important element of the organizational process assets
Lessons learned meetings, focus on identifying individuals, accountable for failures, and errors
Lessons. Learned meetings, include recommendations for future performance improvements.
Phase-end lessons learned workshops represent a good team-building exercise for project members
Answer explanation
lessons learned sessions are performed for the purpose of learning from mistakes in order to avoid repeating them in the future. They also serve as an opportunity to identify and establish best practices and build trust with stakeholders and team members. Lessons learned meetings should not be used to hold others accountable for mistakes made during the project (PMBOK 7th edition, page 180).
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After a long wait, the project manager gets a phone call from the project sponsor confirming that the budget has been allocated, Therefore, the project can get started. The sponsor also informs the project manager that the project development approach should be defined as soon as possible, and that the kickoff meeting should take place within the next two weeks. The project manager replies by saying that he must first receive the project charter.
What is the purpose of a project charter?
To document the project approach
The formally authorize the project and document its initial requirements
To be used as a reference during the project kickoff meeting
To set up the project of conduct
Answer explanation
The project charter is used to formally authorize both the project manager to start the project, as well as document, the project objectives in its high-level scope. It also defines the responsibilities and roles of all involved parties in the project (PMBOK 7th edition, page 184).
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
As part of the project quality control process, the project manager of MCN electric motorcycles decided to check only 10% of the manufactured motorbikes for environmental control.
Which technique is the project manager using?
Sample selection
Control chart
Statistical sampling
Pareto Diagram
Answer explanation
statistical sampling is a technique that involves testing a small sample of a product in order to make a prediction about the total production. Other statistical sampling methods include systematic sampling, cluster sampling, stratified sampling, and judgmental sampling.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A local school is planning to use a screening system to select vegetables and fruit suppliers for their healthy minds organic meals project. Which of the following is an example of a screening system?
You interview all the vendors, and make your decision based on these interviews
You negotiate with all the vendors and engage the one who offers the best price
Consider vendors with more than 10,000 in revenue in the last financial year
You engaged a vendor who response to your announcement
Answer explanation
A screening system is the process of shortlisting vendors based on predefined criteria, such as price, technical capability, financial capacity, available, resources, etc. When certain criteria are more important than others, the criteria should be weighted. choosing the vendor that responds first to your announcement means you are just selecting and not shortlisting vendors when you only select the first 10 vendors who respond to your announcement, it is considered a screening system. Such as selection, however, is neither rational nor reliable, since it won't allow you to shortlist the best, most qualified vendors.
Create a free account and access millions of resources
Similar Resources on Quizizz
60 questions
SFDC Admin Practice Test 1

Quiz
•
Professional Development
60 questions
8202-20 June 2018

Quiz
•
Professional Development
60 questions
Assessment NPO Subcontractor - 25

Quiz
•
Professional Development
60 questions
Google Cloud Professional Cloud Security Engineer (Part 5)

Quiz
•
Professional Development
60 questions
SG20 Baseline Top60 -- The Hardest Questions Ever!

Quiz
•
Professional Development
60 questions
Weekend Quiz W2

Quiz
•
Professional Development
60 questions
PRINCE 2 - Sample Paper 1 (60Q)

Quiz
•
Professional Development
58 questions
BT (Mock - 3) 2023

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade