Final Week Day 1

Final Week Day 1

Professional Development

25 Qs

quiz-placeholder

Similar activities

PMP Questions Agile Management

PMP Questions Agile Management

Professional Development

20 Qs

Project Procurement Management 2022

Project Procurement Management 2022

Professional Development

20 Qs

Scrum Team Quiz 1

Scrum Team Quiz 1

Professional Development

21 Qs

All-in-one CAPM/PMP: Chapter 3

All-in-one CAPM/PMP: Chapter 3

Professional Development

20 Qs

SPM Role Introduction

SPM Role Introduction

Professional Development

20 Qs

Communication

Communication

Professional Development

20 Qs

PMP Questions Agile Management 3

PMP Questions Agile Management 3

Professional Development

20 Qs

Quiziz Week 2 Day 3

Quiziz Week 2 Day 3

Professional Development

20 Qs

Final Week Day 1

Final Week Day 1

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Dedy Hartanto

Used 1+ times

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When is a Sprint over ?
When the product owner says it is done
When the time-box expires
When all the tasks are completed
When all Product Backlog items meet their definition of "Done"

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A Scrum master is working with a Development Team that has members in different physical locations. The Development Team meets in variety of meeting rooms and has much to do lgistically (for example, set up conference calls) before the Daily Scrum. What Action should the Scrum Master Take ?
Set up the meeting and tell the Development team thas is how it will done
Allow the Development Team to Self-manage and determine for itself what to do
Inform management and ask them to solve it
Ask the Development Team members to alternate who is responsible fir meeting setup

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Who owns the Sprint Backlog ?
The Product Owner represents their opinions
Scrum Master
Scrum Team
The Development Team

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When a Development Team determines that it will not be able to finish the complete forecast, whi has to be present when reviewing and adjusting the Sprint work selected
The Development Team
The Product Owner and the Development Team
The Product owner and all stakeholders
The Scrum Master, Project manager and Development Team

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An Agile team is discussing a user story planned for the next iteration. Although the user story appears to be clear, the product owner has yet to address a few related questions on the user story. The agile coach recomends redefining the final requirements with the product owner before making the decision. Which of the following agile principle is described in this scenario ?
The last responsible moment
The last possible moment
Use a release plan
Respect the decision of a self-organizing team

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is performing the Acquire Resources process. Based on similar previous projects undertaken by the organization using its own resources, the resources management plan reflects the need for a Scrum development team with 160 hours of fully dedicated work per week based on a standard 40-hour workweek. What is the project manager’s best course of action ?
Accept any resources that are currently available in the organization
Ask for eight developers who each will work on the project 20 hours a week
Request four developers that can be fully allocated to the project
Outsource the work to an external vendor who is experienced in Scrum

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

As part of the Estimate Activity Durations process, the project manager facilitates a sprint planning meeting with the product owner and Scrum team. The project manager breaks down the user stories into low-level tasks, estimates the time required in hours, and determines the sprint backlog based on the team’s capacity. Despite meticulous planning, the sprint fails._x000B_What might the project manager have done differently ?
Asked the team to prioritize the product backlog before determining the sprint backlog
Assigned the identified low-level tasks to specific individuals in the project schedule
Empowered the team to determine how many user stories they can complete during the sprint
Used story points instead of hours while estimating the size of the user stories and tasks

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?