10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What are the four main qualities that a good Project board should possess?

Authority, Availability, Connections, Ability to delegate

Authority, Credibility, Commitment, Availability

Authority, Credibility, Ability to delegate, Availability

Authority, Credibility, Connections, Ability to delegate

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Whose responsibility is it to ensure that the Communication Management Strategy is suitable and that the defined communication activities actually happen?

Project Manager

Corporate or Programme Management

Project Assurance

Project Support

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What principle serves as the foundation for the quality theme and provides an explicit understanding of what the project seeks to achieve?

Manage by stages

Learn from the experience

Manage by exception

Focus on products

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Who decides what the tolerances are for a work package?

The project board

The project manager

The team manager

Corporate or program management

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

In a project at a window manufacturer to deliver customised windows for a local council, a team manager responsible for the work package to construct the window frames has realised his team won’t be able to produce their frames on time due to difficulties in sourcing the particular type of metal the client requires. The team manager raises this delay as an exception to the Project Manager. Is this action appropriate?

Yes

No

Answer explanation

Team manager raises an issue to the project manager. Project manager raises an exception report to the project board should they forecast the stage will go out of tolerance.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

In an organsation with a programme environment and they have a number of small projects. They wish to speed up the communication between the projects and the programme. They wish to let some project managers report directly to the programme. Is this ok?

Yes

No

Answer explanation

No! You shouldn’t jump levels in communication. Any communication with programme level should come from the Project Board. Maybe the programme level wants to tell the project manager to make a particular high level decision, but that is the responsibility of the project board.

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

In a joint venture project between two organisations, the project manager decides to create two risk registers – one for the joint venture and one for risks just from their own organisation’s point of view. Is this ok to do?

Yes

No

Answer explanation

Yes, because there may be information specific to one party that they don’t want to share with the other party (such as budget or funding issues, or key people leaving, so you don’t want to let the other party know too early on of certain internal confidential or delicate risks or issues).

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?