1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the best example of a blocker?

The team cannot decide when to schedule the next iteration review.

The demonstration is not ready for the iteration review.

Clearance from another team to use content for the demo won’t be ready within the current iteration.

The demonstration fails in front of the product owner during the iteration review.

2.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which two of the following are types of project metrics that may be appropriate for a given project? (Choose two)

Percentage of work completed

Defects

Subcontractor approvals

Process compliance

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an ideal location for an information radiator?

In the manager’s office

In a high-traffic area

In an unused conference room

On the project manager’s laptop

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A problem occurs during the project execution. It is not a big problem, but it does bother some of the stakeholders. The project manager requests that it be added to the issue log. What would be the reason for this?

The issue log serves as a place to document problems that occur and to track their resolution.

The issue log will be reviewed by the risk team at its next meeting to develop a contingency plan.

The issue log will be submitted to the change control board for a change approval.

The issue log serves as a place to document the unidentified risks.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When does a risk become an issue?

The project manager judges the risk to be significant enough that it is stipulated to be an issue.

The risk has a high probability of happening in the immediate future.

The risk has occurred.

The risk owner escalates the risk to an issue.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How do you describe an effective change control system?

An effective change control system includes the forms, tracking methods, processes, and approval levels required for authorizing or rejecting requested changes.

An effective change control system includes the documented procedures for authorizing or rejecting requested changes in a project.

An effective change control system specifies how the project scope will be controlled, changed, and approved.

An effective change control system integrates all the changes for a project.

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Who can request changes? (Select all that apply)

Team members and project managers

Sponsor

Stakeholders

Customer

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?