Implementation PM

Implementation PM

University

16 Qs

quiz-placeholder

Similar activities

Statistics Quiz

Statistics Quiz

University

20 Qs

Passive Voice(S. Present& S. Past)

Passive Voice(S. Present& S. Past)

University

16 Qs

Life of Jesus

Life of Jesus

KG - University

14 Qs

Chapter 4

Chapter 4

University

20 Qs

Rehab 105 Short Quiz 4 - Endterms

Rehab 105 Short Quiz 4 - Endterms

University

20 Qs

Psych drugs

Psych drugs

University

14 Qs

Freight Rate

Freight Rate

University

16 Qs

Project mc²

Project mc²

2nd Grade - Professional Development

11 Qs

Implementation PM

Implementation PM

Assessment

Quiz

Other

University

Practice Problem

Medium

Created by

ash ly

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

16 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 2 pts

Media Image

What is the role of the Project Manager during Implementation? Choose two (2) among the choices.

Produce Deliverables

Sell Products

Create Project Charter

Monitor and Control

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

This phase is also known as Project Execution. It is where the actual work is done to produce the deliverables.

Planning Phase

Initiation Phase

Implementation Phase

Close out

3.

FILL IN THE BLANK QUESTION

1 min • 3 pts

Media Image

The unit of measure should be related to the ___________.

4.

MATH RESPONSE QUESTION

2 mins • 2 pts

Media Image

Reported completion at the end of the day :

Clearing = 100 sq m

Excavation = not yet started

Fencing = not yet started

Compute for the percentage accomplishment of the project_%.

Mathematical Equivalence

OFF

5.

MATH RESPONSE QUESTION

2 mins • 4 pts

Media Image

Reported completion at the end of 4th day.

Clearing = 100 sq.m

Excavation = 2.5 cu.m

Fencing = not yet started

Compute for the percentage accomplishment of the project_%.

Mathematical Equivalence

OFF

Answer explanation

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Tracking the budget means:

Regularly compare the amount of money spent with the budgeted amount.

Regularly compare the percent of completion with the budgeted amount.

Regularly compare the resources with the budgeted amount.

Monthly comparison of the percent of completion with the budgeted amount.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

This is a regular activity in project management, and during this activity it is where the team works together in identifying problems and issues and create solutions.

Risk and Issue management

Quality Control

Team Meetings

Stakeholder Engagement

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?