1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In project management, which of the following is NOT applied to project activities to meet?
Benefits
Knowledge
Tools
Techniques
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the first phase of a project?
Closing
Controlling
Executing
Initiating
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project's Net Present Value (NPV) can be negative.
True
False
Maybe
Occasionally
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How many owners should a task be assigned to?
One
Two
Three
Unlimited
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Quality is doing the right things right and is uniquely defined by each individual.
True
False
Maybe
Occasionally
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following quality tool is used to predict potential flaws in a process?
Flow Chart
Pareto Chart
Statistical sampling
Cause & effect diagram
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT a quality tool?
Guest satisfaction survey
Food preparation process flow-chart
Gantt Chart for adhering to timelines
Housekeeping room cleaning checklist
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?