1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Shayna is an event project manager. She is meeting with her conference
stakeholders to ensure the scope of products delivered aligns with what
was planned for in the scope baseline of the project. Which process is
Shayna conducting?
collect requirements
control scope
define scope
verify scope
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Peter, a project manager, meets with his client to get the client's
signature at the completion of a phase of work. Which phase is the
project in?
planning
executing
monitoring and controlling
closing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Brian is determining the process for handling scope change requests.
Which process is Brian conducting?
collect requirements
control scope
define scope
verify scope
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Amy is a catering project manager in charge of a charity event. She taste
tests the cupcakes made by Sammy, a member of her catering team. Amy
determines that Sammy over blended the cupcakes because the tops
have risen. She asks Sammy to fix the cupcakes according to the project
scope before moving the cupcakes to production. Amy is using which tool
or technique?
decomposition
estimating
inspection
variance analysis
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Mark meets with the conference project stakeholders to determine and
document that the number of rooms and meals needed for the
conference aligns with the conference project objectives. Which process
is Mark conducting?
collect requirements
control scope
define scope
verify scope
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Sarah is in charge of a charity event, and she is currently communicating
with the catering company and requesting work performance information
regarding their progress to compare to her scope baseline. Sarah is
working on which process?
collect requirements
control scope
define scope
verify scope
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Lisa is a financial project manager. Bella asks Lisa's team to produce a
financial report at the end of the year that includes her company's
income statement and balance sheet. When Lisa's team completes the
work and the deliverables are presented to Bella , Lisa asks Bella to sign
off to formally accept the project deliverables. Which process is Lisa
conducting?
collecting requirements
controlling the scope
defining the scope
verifying the scope
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?