1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Shayna is an event project manager. She is meeting with her conference

stakeholders to ensure the scope of products delivered aligns with what

was planned for in the scope baseline of the project. Which process is

Shayna conducting?

collect requirements

control scope

define scope

verify scope

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Peter, a project manager, meets with his client to get the client's

signature at the completion of a phase of work. Which phase is the

project in?

planning

executing

monitoring and controlling

closing

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Brian is determining the process for handling scope change requests.

Which process is Brian conducting?

collect requirements

control scope

define scope

verify scope

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Amy is a catering project manager in charge of a charity event. She taste

tests the cupcakes made by Sammy, a member of her catering team. Amy

determines that Sammy over blended the cupcakes because the tops

have risen. She asks Sammy to fix the cupcakes according to the project

scope before moving the cupcakes to production. Amy is using which tool

or technique?

decomposition

estimating

inspection

variance analysis

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Mark meets with the conference project stakeholders to determine and

document that the number of rooms and meals needed for the

conference aligns with the conference project objectives. Which process

is Mark conducting?

collect requirements

control scope

define scope

verify scope

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Sarah is in charge of a charity event, and she is currently communicating

with the catering company and requesting work performance information

regarding their progress to compare to her scope baseline. Sarah is

working on which process?

collect requirements

control scope

define scope

verify scope

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Lisa is a financial project manager. Bella asks Lisa's team to produce a

financial report at the end of the year that includes her company's

income statement and balance sheet. When Lisa's team completes the

work and the deliverables are presented to Bella , Lisa asks Bella to sign

off to formally accept the project deliverables. Which process is Lisa

conducting?

collecting requirements

controlling the scope

defining the scope

verifying the scope

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?