Full Length Exam 3 dengan 175 soal

Full Length Exam 3 dengan 175 soal

Professional Development

175 Qs

quiz-placeholder

Similar activities

PMP Exam-1 dengan 180 soal

PMP Exam-1 dengan 180 soal

Professional Development

180 Qs

April 1st week

April 1st week

Professional Development

170 Qs

Full Length Exam 3 dengan 175 soal

Full Length Exam 3 dengan 175 soal

Assessment

Quiz

Education

Professional Development

Medium

Created by

Riskita Adela

Used 1+ times

FREE Resource

175 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project is in the execution phase when the project manager realizes that several of the stakeholders identified at the start of the project were removed from the project. The stakeholders that have been removed from the project are frustrated with the unnecessary communication and express concern that the remaining stakeholders may not be receiving all of the information they require.

What should the project manager have done to prevent this?

Identified and documented all stakeholder requirements at the start of the project.

Reported all project information to every stakeholder throughout the project lifecycle.

Updated the stakeholder engagement plan through the change control process

Relied on existing stakeholders to inform the project manager about missing stakeholders

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is working on an agile project with a cross-functional team. The project manager is informed that some team members typically raise additional requirements that are not in the approved scope.

What should the project manager do to address this expected behavior?

Coach the team to manage scope using the appropriate framework

Escalate to the sponsor and request replacement team members

Conduct daily standup meetings with the team and stakeholders.

Explain that requirements cannot be changed without approval

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project team has completed the project deliverables per the requirements specified by the project sponsor. The project manager would like to evaluate whether the project has delivered value to the sponsor. What is the most appropriate element for the project manager to evaluate?

The alignment of all accomplished deliverables with the initial requirements.  

Whether the project's deliverables maximized potential income for the sponsor

The extent to which the delivery of value matched the sponsor's expectations

The project's overall adherence to scope, time, and budget constraints

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An events company is designing a new event for a client that holds biannual conferences. The project is being managed by a new project manager who, after reviewing the last event that occurred 6 months ago, is concerned about issues that may reoccur.

What type of session should the project manager facilitate?

Retrospective

Backlog grooming

Release planning

Standup

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In a software development project, a stakeholder wants to add a major requirement, which they feel will be a great benefit to the project. However, this requirement is not aligned to the project objectives that the business owner has documented.

What should the project manager do next?     

Ensure the stakeholder understands the purpose of the project

Encourage the stakeholder to follow the written business requirements.

Include the additional requirement into the project and inform the business owner.

Fast-track the project and suggest the new requirement to the business owner

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An ongoing project has a high degree of change. In order to evaluate how the IT security team will influence the performance of the project, what should the project manager do?

Update the stakeholder engagement assessment matrix.

Analyze corporate political and power structures.

Create a project communications management plan.

Manage stakeholders' expectations.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager has identified that a task on the critical path is behind schedule. The project manager thinks that additional resources will help, but higher management declined a request for the additional funding necessary to add resources. The project manager must work with the approved resources and budget.

What would be the best-suited practice for the project manager to address this situation?

Resource leveling

Crashing

Fast tracking

What-if scenario analysis

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?