1.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What is the purpose of estimating costs for a budget?

To analyze project performance over time

To influence and manage changes related to cost

To calculate the cost estimate for each activity

To determine the total project budget amount

2.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What is the Cost of Quality (COQ) used for in preparing the activity cost estimate?

To calculate the cost estimate for each activity

To determine the total project budget amount

To analyze project performance over time

To make assumptions about costs of quality

3.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What is the Cost performance baseline used for?

To determine the total project budget amount

To analyze project performance over time

To calculate the cost estimate for each activity

To measure, monitor, and control overall cost performance on the project

4.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What is the purpose of Earned Value Management (EVM)?

To analyze project performance over time

To determine the total project budget amount

To assess and measure project performance and progress

To calculate the cost estimate for each activity

5.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What does the Schedule Variance (SV) measure?

Schedule performance of a project

Projection of cost performance that must be achieved on the remaining work

Progress achieved compared to progress planned on a project

Cost performance on a project

6.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What does the Cost Variance (CV) measure?

Projection of cost performance that must be achieved on the remaining work

Progress achieved compared to progress planned on a project

Cost performance on a project

Schedule performance of a project

7.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

What is the purpose of Performance Reviews in cost control?

To compare the cost performance over time

To compare the schedule activities or work packages

To examine project performance over time

To compare the baseline plan to actual schedule and cost performance

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?