
Quiz 5 - Project Management
Authored by Sergio Monteiro
Life Project
University
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
18 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000?
Cost Variance
Management Overhead
Management Contingency Reserve
Schedule Variance
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If the Earned Value is equal to Actual Cost, it means:
Project is on budget and on schedule
Schedule Variance Index is 1
There is no schedule variance
There is no cost variance
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If earned value EV = 350, actual cost AC = 400, planned value PV = 325, what is cost variance CV ?
350
-75
400
-50
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the best way to maintain control of costs?
Evaluate monthly expenditures based on a carefully formulated program
Personally review all expenditures before any disbursements are made
Assign all authority to one staff memeber
Submit weekly expenditures to superior for review
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You found out that your project is one week late, as an effective project manger, what would you do?
Evaluate resources and options
Analyze why the deadline was not met
Inform the client that the project will be one week late
Ask to work overtime
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
As a project manager you are estimating the cost of your project activities using BETA distribution. For a particular project activity, your optimistic estimate is 41, pessimistic estimate is 77 and most Likely estimate is 53. What would be the expected cost for this activity?
171
55
59
57
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following are the MOST important to deriving the total funding requirements and periodic funding requirements of the project?
Management Reserve and Contingency Reserve
Cost Baseline and Management Reserve
Funding Limit Reconciliation
Project Budget and Contingency Reserve
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?