Procurement and tendering

Procurement and tendering

Professional Development

10 Qs

quiz-placeholder

Similar activities

April PKT

April PKT

Professional Development

10 Qs

The Pink Gene Pre-test

The Pink Gene Pre-test

KG - Professional Development

10 Qs

Process procurement and Dev Term3 W3

Process procurement and Dev Term3 W3

Professional Development

10 Qs

FFA

FFA

Professional Development

10 Qs

Kuis SCDC

Kuis SCDC

University - Professional Development

6 Qs

PROJECT MANAGEMENT 01

PROJECT MANAGEMENT 01

University - Professional Development

10 Qs

Project Finance (control and reporting)

Project Finance (control and reporting)

Professional Development

10 Qs

Construction Cost Estimating and Analysis Quiz No. 1

Construction Cost Estimating and Analysis Quiz No. 1

Professional Development

10 Qs

Procurement and tendering

Procurement and tendering

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

CBE QS

Used 32+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

This means the processes from identification of a project up to receipt of tenders and award of contracts for its implementation. Which of the following best describes this?

Tendering

Assignment

Procurement

Novation

2.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

How is the contractor selected through the bidding process and appointed?

Contract Award

Procurement

Tendering

Purchase

3.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

The sequential nature of the strategy, which is necessary to assure low risk, does mean that it can be relatively slow before the commencement of construction.

Traditional

(Lump Sum)

Traditional (Remeasurement)

Design and Build

Construction Management

4.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

This contractor may have a legal duty to provide the employer with a building that is fit for its purpose.

Traditional

(Lump Sum)

Traditional (Remeasurement)

Design and Build

Construction Management

5.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

This is most often adopted for large or complex projects. It has particular benefits for projects where there is a high degree of design innovation, where the client wants ‘hands-on’ involvement, or where design flexibility is needed throughout the project process.

Traditional

(Lump Sum)

Traditional (Remeasurement)

Design and Build

Construction Management

6.

MULTIPLE SELECT QUESTION

1 min • 20 pts

Procurement routes on a Financial basis (select all that are applicable):

Lump Sum

Traditional Remeasurement

Cost Reimbursable

Target Cost

7.

MULTIPLE CHOICE QUESTION

1 min • 20 pts

These are arrangements where a project or service is provided by the private sector in partnership with the public sector.

Public Private Partnerships (PPP)

Construction Management

Private Finance Initiative (PFI)

Management Contracting

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?