Pre-test Cost & Quality Management

Pre-test Cost & Quality Management

Professional Development

15 Qs

quiz-placeholder

Similar activities

10 soal campuran (June)

10 soal campuran (June)

Professional Development

10 Qs

Project Closure

Project Closure

Professional Development

10 Qs

Scope Management Plan

Scope Management Plan

Professional Development

15 Qs

Project Planning Unit1&2

Project Planning Unit1&2

Professional Development

10 Qs

November W III - 1

November W III - 1

Professional Development

15 Qs

Project Management - 2nd Day

Project Management - 2nd Day

Professional Development

17 Qs

Nokia ID SG_Quiz All Chapter

Nokia ID SG_Quiz All Chapter

Professional Development

20 Qs

PMP Questions 6th Edition Quiz 3

PMP Questions 6th Edition Quiz 3

Professional Development

20 Qs

Pre-test Cost & Quality Management

Pre-test Cost & Quality Management

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

SG21 PMIIC

Used 1+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following inputs to the Plan Cost Management process provides preapproved financial resources?

Organizational process assets

Project management plan

Project charter

Enterprise environmental factors

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is leading a research and development project. The value of the work completed on the project thus far is $450,000, and the cost baseline is $2,000,000. At this point in the project, you have spent 22% of the budget at completion (BAC). The value of work planned to be completed at this point is $475,000.

Based on this information, which of the following is not true?

The SPI is 0.95

The CPI is 1.02

The SV is $25,000

The CV is $10,000

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A team member responsible for tracking the costs of a project increases the budget to accommodate the unexpected rise in expenditures over the last three weeks.

What should the project manager say to the project team members unexpected rise?

Any increase to the authorized budget can only be approved via the Perform Integrated Change Control process

If the increase in the budget is to cover an unexpected rise in expenditures, the project sponsor should be consulted

Adjustments to the project budget need to occur closer to the point when expenditures go above budget

Any increase in the authorized budget requires the development of an earned value analysis report (EVA) first

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Resource costs continue to rise and are expected to increase further.

What can the project team do to control the costs?

Hold the cost baseline steady

Conduct an alternative analysis

Request more funds from the customer

Utilize management reserves

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

There have been quality problems with one of the deliverables on your project. A project team member has informed you they have discovered a workaround that will bring the product back to acceptable limits. The possibility of quality issues with this product was not identified as a risk. Both the workaround and the rework require an increase in costs.

What is the best course of action for the project manager when funding this unforeseen workaround and rework?

Use contingency reserves and submit a change request to adjust the cost baseline

Utilize contingency reserves without adjusting the cost baseline or submitting a change request

Transfer funds from the management reserve and submit a change request to adjust the cost baseline

Take funds from the management reserve without adjusting the cost baseline or submitting a change request

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

As the last sprint of the project is about to end, the company realizes that the product does not comply with the data privacy laws of the country where the product is to be deployed. Due to budget constraints, the company has to decide on whether to pay for the incompliance fines or do rework. Rework would involve significant changes to the performance baseline.

In this situation, which of the following is most likely to help?

Stacey matrix

Personas

A phase gate

Fast tracking

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

At this point in the project, the system analysis, design, and development should have been completed. However, according to the table shown below, system development is only 50% complete, and the actual cost of system analysis is higher than planned. You believe that the remaining project work will be influenced by these low-cost and schedule performance values.

Which of the formulas should be used to determine the estimate at completion (EAC)?

EAC = AC + [(BAC - EV) / (CPI x SPI)]

EAC = BAC / CPI

EAC = AC + BAC - EV

EAC = BAC

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?