Which of the following inputs to the Plan Cost Management process provides preapproved financial resources?

Pre-test Cost & Quality Management

Quiz
•
Professional Development
•
Professional Development
•
Hard
SG21 PMIIC
Used 1+ times
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Organizational process assets
Project management plan
Project charter
Enterprise environmental factors
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is leading a research and development project. The value of the work completed on the project thus far is $450,000, and the cost baseline is $2,000,000. At this point in the project, you have spent 22% of the budget at completion (BAC). The value of work planned to be completed at this point is $475,000.
Based on this information, which of the following is not true?
The SPI is 0.95
The CPI is 1.02
The SV is $25,000
The CV is $10,000
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A team member responsible for tracking the costs of a project increases the budget to accommodate the unexpected rise in expenditures over the last three weeks.
What should the project manager say to the project team members unexpected rise?
Any increase to the authorized budget can only be approved via the Perform Integrated Change Control process
If the increase in the budget is to cover an unexpected rise in expenditures, the project sponsor should be consulted
Adjustments to the project budget need to occur closer to the point when expenditures go above budget
Any increase in the authorized budget requires the development of an earned value analysis report (EVA) first
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Resource costs continue to rise and are expected to increase further.
What can the project team do to control the costs?
Hold the cost baseline steady
Conduct an alternative analysis
Request more funds from the customer
Utilize management reserves
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
There have been quality problems with one of the deliverables on your project. A project team member has informed you they have discovered a workaround that will bring the product back to acceptable limits. The possibility of quality issues with this product was not identified as a risk. Both the workaround and the rework require an increase in costs.
What is the best course of action for the project manager when funding this unforeseen workaround and rework?
Use contingency reserves and submit a change request to adjust the cost baseline
Utilize contingency reserves without adjusting the cost baseline or submitting a change request
Transfer funds from the management reserve and submit a change request to adjust the cost baseline
Take funds from the management reserve without adjusting the cost baseline or submitting a change request
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
As the last sprint of the project is about to end, the company realizes that the product does not comply with the data privacy laws of the country where the product is to be deployed. Due to budget constraints, the company has to decide on whether to pay for the incompliance fines or do rework. Rework would involve significant changes to the performance baseline.
In this situation, which of the following is most likely to help?
Stacey matrix
Personas
A phase gate
Fast tracking
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
At this point in the project, the system analysis, design, and development should have been completed. However, according to the table shown below, system development is only 50% complete, and the actual cost of system analysis is higher than planned. You believe that the remaining project work will be influenced by these low-cost and schedule performance values.
Which of the formulas should be used to determine the estimate at completion (EAC)?
EAC = AC + [(BAC - EV) / (CPI x SPI)]
EAC = BAC / CPI
EAC = AC + BAC - EV
EAC = BAC
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
10 soal campuran (June)

Quiz
•
Professional Development
10 questions
Introduction to Lean & Six Sigma

Quiz
•
Professional Development
10 questions
Project Closure

Quiz
•
Professional Development
15 questions
Scope Management Plan

Quiz
•
Professional Development
20 questions
PMP Assessment

Quiz
•
Professional Development
10 questions
TEST DAY 1 MT

Quiz
•
Professional Development
18 questions
Chapter 1-3

Quiz
•
Professional Development
20 questions
Pre-Test Project Management [15/04/25]

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade