10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Samuel, Ethan, and Liam are working on a group project. What should be their primary concern in managing the scope of their project?

Controlling their budget

Defining and controlling what is included in their project

Managing potential risks

Ensuring the quality of their work

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Lucas is the project manager of a software development team. He wants to formally authorize a new project or the continuation of an existing project. Which process should he follow?

Closing

Execution

Planning

Initiation

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Arjun, Chloe, and Rohan are working on a school project. What do they call the process of progressively elaborating and documenting their project work?

Scope definition

Scope change control

Scope verification

Scope planning

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Neha, Ella, and Lily are working on a school project. What does their task of scope definition involve?

Managing risks associated with their project

Monitoring the progress of their project

Subdividing their project into major deliverables

Improving communication within their project team

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the process of obtaining formal acceptance of the project scope by stakeholders?

Scope definition

Scope change control

Scope planning

Scope verification

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is scope change control concerned with?

Influencing factors that create schedule changes

Quality assurance control

Determining project budget changes

Managing actual scope changes

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does the product scope refer to?

Project deliverables and work required

Features and functions of the product

Project constraints and assumptions

Project stakeholders and their roles

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?