Project Lifecycles

Project Lifecycles

University

8 Qs

quiz-placeholder

Similar activities

Project Management - Test

Project Management - Test

University - Professional Development

10 Qs

PJMT 2103: Week 5: PM Time Management

PJMT 2103: Week 5: PM Time Management

University

10 Qs

IT Project Failure Research Quiz

IT Project Failure Research Quiz

University

10 Qs

Technical Specifications

Technical Specifications

University

10 Qs

MICE-FINAL EXAM

MICE-FINAL EXAM

University

13 Qs

Project management 101

Project management 101

University - Professional Development

12 Qs

Planning & Scheduling (Introduction)

Planning & Scheduling (Introduction)

University - Professional Development

10 Qs

Quiz 3 - Hybrid Project Management

Quiz 3 - Hybrid Project Management

University

10 Qs

Project Lifecycles

Project Lifecycles

Assessment

Quiz

Other

University

Medium

Created by

Sha Lacbongan

Used 4+ times

FREE Resource

8 questions

Show all answers

1.

REORDER QUESTION

1 min • 1 pt

Reorder the stages in the lifecycle of a project?

Implementation (Control & Monitoring)

Planning

Initiation

Closure

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important to identify project stakeholders during the initiation stage?

To understand their needs and expectations

To create a project schedule

To assign project tasks and responsibilities

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if there are changes or new requirements in the Waterfall methodology?

Changes are ignored

Changes require significant effort and may delay the project

Changes are easily incorporated without affecting the project timeline

Changes are documented for future projects

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Agile, what is the benefit of frequent customer feedback and adaptation of requirements?

It eliminates the need for project documentation

It ensures strict adherence to the project plan

It allows for changes to better meet customer needs

It minimizes the need for testing

5.

CLASSIFICATION QUESTION

3 mins • 1 pt

Assign the following characteristics as Waterfall or Agile.

Groups:

(a) Agile

,

(b) Waterfall

Flexible/Adaptible

Upfront planning

Constant Review

Linear phases  

Testing at the end

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Agile Methodology

You anticipate changing needs and requirements; a need for multiple deliverables over an extended period; improving processes and workflows.

When collaboration is needed; interdisciplinary coordination and early stakeholder involvement.

Deadlines and resources constraints are known; the project is straightforward and not overly complex; not necessary to work close with stakeholders.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Integrated Project Delivery

You anticipate changing needs and requirements; a need for multiple deliverables over an extended period; improving processes and workflows.

When collaboration is needed; interdisciplinary coordination and early stakeholder involvement.

Deadlines and resources constraints are known; the project is straightforward and not overly complex; not necessary to work close with stakeholders.

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Waterfall Methodology

You anticipate changing needs and requirements; a need for multiple deliverables over an extended period; improving processes and workflows.

When collaboration is needed; interdisciplinary coordination and early stakeholder involvement.

Deadlines and resources constraints are known; the project is straightforward and not overly complex; not necessary to work close with stakeholders.