MULTIPLE CHOICE QUESTION
1 min • 1 pt
The shutters and bottom support of non-cantilever slab is removed within minimum of _ days
7 days
14 days
28 days
21 days
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Shotcrete is used in
Repairing surfaces
Dam surfaces
Curved surfaces
All of the Above
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The shutters and bottom support of non-contiliver beam can be removed within minimum of _
7 days
14 days
28 days
21 days
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Bitumen is used in construction to provide _
Protective Surface
Shining Surface
Decorative Surface
All of the Above
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
First test on concrete is done after _ days
7 days
14 days
28 days
3 days
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Core samples are taken for finding _
tensile strength
compressive strength
water absorption
surface hardness
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Rebound smidth hammer test is _
Destructive test
non-destructive
cohesion test
All of above
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?