1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The shutters and bottom support of non-cantilever slab is removed within minimum of _ days

7 days
14 days
28 days
21 days

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Shotcrete is used in

Repairing surfaces
Dam surfaces
Curved surfaces
All of the Above

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The shutters and bottom support of non-contiliver beam can be removed within minimum of _

7 days
14 days
28 days
21 days

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Bitumen is used in construction to provide _

Protective Surface
Shining Surface
Decorative Surface
All of the Above

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

First test on concrete is done after _ days

7 days
14 days
28 days
3 days

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Core samples are taken for finding _

tensile strength
compressive strength
water absorption
surface hardness

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Rebound smidth hammer test is _

Destructive test
non-destructive
cohesion test
All of above

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?