UNIT 2

UNIT 2

Professional Development

10 Qs

quiz-placeholder

Similar activities

How well do you know R.A. 9184 and its IRR?

How well do you know R.A. 9184 and its IRR?

Professional Development

10 Qs

L4M1 Scope and Influence of Procurement and Supply Recap Week 3

L4M1 Scope and Influence of Procurement and Supply Recap Week 3

Professional Development

10 Qs

Team Dynamics and Change Recap Week 2

Team Dynamics and Change Recap Week 2

Professional Development

10 Qs

Lesson 4:  SD Methodologies. Discussing Waterfall, Agile & Scrum

Lesson 4: SD Methodologies. Discussing Waterfall, Agile & Scrum

Professional Development

10 Qs

Project Management Quiz

Project Management Quiz

Professional Development

15 Qs

Quizizz - Finance Directorate Event

Quizizz - Finance Directorate Event

Professional Development

10 Qs

NEOP - Project Management 2024

NEOP - Project Management 2024

Professional Development

10 Qs

Project Starter

Project Starter

Professional Development

11 Qs

UNIT 2

UNIT 2

Assessment

Quiz

Other

Professional Development

Hard

Created by

Madaí Flores

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the lowest level component in the work breakdown structure (WBS) hierarchy?


Activity

Deliverable

Planning package


Key deliverable

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which conflict resolution technique can result in a win-win situation?

Collaborate/problem solve

Force/direct

Withdraw/avoid

Compromise/reconcile

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which two techniques can be used to shorten a project's duration? (Choose 2.)

Fast-tracking

Crashing


Applying leads and lags

Resource leveling

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which phase of the Tuckman theory do team members tend to work independently?


Forming


Norming

Storming


Performing

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What communication method includes an intranet where you upload documentation?

Pullcommunication

Osmotic communication

Push communication


Interactive communication

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What three actions are types of changes in a project? (Choose 3.)

Corrective action

Prevention action

Change Request

Defect repair

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

In which two situations is it recommended to use a traditional management approach? (Choose two.)

When the project is innovative and features a high amount of uncertainty about the project's scope

When there exists certainty about the scope of the project

When the project features a high amount of uncertainty about what technology to use

When it is possible to plan the project in the early of its lifecycle

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?