
Project Management Quiz - Schedule
Authored by Citizen TV
Other
Professional Development

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
23 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is managing a web-based application project to automate the accounting processes of his organization. The project has an estimated budget of $120,000 and a duration of nine months. While reviewing the project, the project manager notices that activities were scheduled in sequential order, but coding work was initiated twelve days earlier than planned. What type of relationship represents the start of the coding work to the completion of the design work?
Finish-to-start relationship with a twelve-day lag
Finish-to-start relationship with a twelve-day lead
Start-to-finish with a twelve-day lag
Start-to-finish with a twelve-day lead
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
One of your team members is always late completing his deliverables. In order to help him out with proper planning for his activities, you'd like to explore different options with him. You asked the team member to send you information about the total float and free float for all of his activities if there is any. How does free float differ from total float?
Total float and free float are the same thing.
Free float affects only the early start of the successor activities.
Total float is the accumulated amount of free float.
Subtracting the total float from the critical path duration will give the free float.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which one of the following takes the progressive elaboration approach and plans the work in the near term in detail and future work in a higher level?
Scope definition
Rolling wave planning
Decomposition
SWOT analysis
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
One of your team members working on the project informed you that a work package will most likely require ten weeks to complete. In the best-case scenario, if everything goes well and there are no surprises, it will take eight weeks. Since he is involved in more than two projects and has several pending deliverables, this specific work package may take eighteen weeks to complete. Based on this information, what would be the correct estimated time to complete the work package?
Eleven weeks
Ten weeks
Nine weeks
Eighteen weeks
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your project sponsor is extremely disappointed with the project as it is over budget by $20,000 and also behind schedule by several weeks. The sponsor has asked you to take care of the situation immediately. While exploring different options to shorten the project duration, you decide, with management’s approval, to perform several activities in parallel rather than in sequential order as originally planned. You know your option will possibly result in rework, increase risks, and require more communication, but you decide to go for it anyway. This is an example of which of the following?
A. Critical chain method
B. Crashing
C. Resource leveling
D. Fast-tracking
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is in the Sequence Activities process of identifying and documenting relationships among defined activities and arranging them in the order they must be performed. While in this process, the project manager decided to utilize a software tool to create a Precedence Diagramming Method (PDM) network diagram. This network diagram creates a schematic display of the sequential and logical relationships, dependencies, and the order in which activities in a project must be performed. The project manager also added the duration of each activity in the network diagram to calculate the critical path. Which one of the following is FALSE about the critical path?
It is the longest duration path through a network diagram.
It determines the shortest time to complete the project.
The activities on the critical path represent the highest schedule risk in the project.
The activities on the critical path represent critical functionality.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You just completed developing the schedule for your project and got the approval from stakeholders and the sponsor. One of the team members assigned to work on a critical component informs you that she needs additional time to complete her activities as several relevant pieces were missed during planning. Her updated estimate would have no impact on the critical path; thus, the project duration would be the same. The best approach the project manager may take in this situation will be:
A. Find a replacement for the resource who can complete the task within the allocated time.
B. Inform the resource that it is too late for any kind of change in the project schedule.
C. Inform her that it is OK as you have sufficient schedule reserve to handle this kind of situation.
D. Update the project schedule and other relevant plans to reflect the new estimate.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
20 questions
Environment, Health & Safety in Industries - First Internal
Quiz
•
Professional Development
20 questions
MS Excel Quizz
Quiz
•
Professional Development
21 questions
Guess the Anime Character
Quiz
•
KG - Professional Dev...
20 questions
General knowledge quiz
Quiz
•
Professional Development
21 questions
ALS
Quiz
•
University - Professi...
20 questions
SETVIZ Quiz
Quiz
•
Professional Development
20 questions
TechMD-IEC Module 1 Quiz
Quiz
•
Professional Development
20 questions
Spring/Summer 2024 Lessons and Sits
Quiz
•
Professional Development
Popular Resources on Wayground
7 questions
History of Valentine's Day
Interactive video
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
15 questions
Valentine's Day Trivia
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
Discover more resources for Other
44 questions
Would you rather...
Quiz
•
Professional Development
20 questions
Black History Month Trivia Game #1
Quiz
•
Professional Development
12 questions
Mardi Gras Trivia
Quiz
•
Professional Development
14 questions
Valentine's Day Trivia!
Quiz
•
Professional Development
7 questions
Copy of G5_U5_L14_22-23
Lesson
•
KG - Professional Dev...
16 questions
Parallel, Perpendicular, and Intersecting Lines
Quiz
•
KG - Professional Dev...
11 questions
NFL Football logos
Quiz
•
KG - Professional Dev...
12 questions
Valentines Day Trivia
Quiz
•
Professional Development